   Weekly Progress Report as on 05.04.2013
    
ROB at Sulthanpet - Palaghat Town    
Staging drawing approval from Railways pending 1 no yet to be received (RP3-RP4) 
Retaining wall (Palakkad side)  In progress 100% work done
Kerb Casting (Palakkad side) Completed  
Handrail fixing (Palakkad side) Completed  
Drain work  (Moyan school  side)  In progress done 40%
Retaining wall,Kerb & Handrail (Moyan school  side)  Completed 100% completed
Bowstring girder (RP4-RP5) Completed Done upto bow arch bracing
Handrail fixing & kerb casting Completed 4 slabs of Moyen's side and 2 slabs of Pkd side completed.
Bowstring girder Stressing and grouting Completed  
RP6-RP7-RP8 railway slab Completed  
RP6-RP7-RP8 Kerb & paparapet wall Completed  
RP7-P5, P5-P6, P6-P7, P7-P8 Deck slab and girder completed Moyen's school side deck slabs
Crash barier for RP6-RP7-RP8 Completed  
P1-P2, P4-RP1 Deck slabs and girder Completed Pkd side deck slabs
RP5-RP6 girder & deck slab work Completed  
RP5-RP6 Crash barrier  Completed  
RP5-RP6 Kerb & paparpet wall Completed  
RP4-RP5 Deck slab casting Completed Bowstring girder
RP4-RP5 slab lowering Completed  
RP4-RP5 crash barrier/kerb casting In progress  
Approach filling Completed Moyen's school side & Pkd side
WBM for approach Completed Moyen's school side & palakkad side
Cantilver portion of P7-P8 & P1-P2 completed  
Diversion road WBM Completed Moyens side
Painting works Stopped Moyens & Palakkad side
Ret wall LHS & RHS side I, II & III port In progress III arm
Piling works in P10, P11, P12 locations Completed III arm (12 No.s)
Pile cap works in P10 P11 & P12 location Completed III arm 
Pier P10 P11 & P12 Completed  
RP8-P9 girder and deck slab casting Completed  
RP1-RP2 girder and slab casting Completed  
RP1-RP2 stressing and grouting Completed  
Pier cap P10, P11, P12 Completed  
P9-P10 & P10-P11 girder and slab casting Completed  
RP2-RP3 Girder & slab work Completed  
RP3-RP4 temp. footing In progress 45% done
P11-P12 girder & slab casting Completed  
 
Back
 
    
RP1-RP2 FOOTPATH SLAB LAYING

    
    
RET. WALL HANDRAIL CASTING

      
 

 

 

 

 

 

 

 