Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7887508
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly Progress Report as on 29.03.2013
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 - - - - - -
4 PierCap 21 21 - - - - - -
5 Deck Slab 21 19 2 - - - - -
6 Hand Rails 21 19 2          
7 Expansion Joint 21 18 3   1 1 0 0
8 RC wall -
Kuttipuram side
100% 78% 22% - 15% 8% 7% 15%
9 RC wall -
Kanjipura side
100% 90% 10%   5% 5% 0% 5%
                   
                   
Date 23.03.13 25.03.13 26.03.13 27.03.13 28.03.13 29.03.13      
Climate Pleasant Pleasant Pleasant Pleasant Pleasant Pleasant      
No. of labours 30 30 30 30 25 25      
                   
                   
Availability of Materials                
                   
Material Required Available              
Fine
aggregate
15 m3 20 m3              
Coarse
Aggregate
32 m3  34 m3              
Cement 150 bags 200 bags              
Steel 10MT 25 MT              
 
Back
 
    
RETAINING WALL

    
    
BOX CULVERT REINFORCEMENT WORK

      
 

 

 

 

 

 

 

 