Prevoius Weekly Reports

   Weekly report as on 29-03-2013
    
Progress Report For Koilandy ROB for the week ending on 29-03-2013  
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaining for completion as per the weekly plan Remarks 
1 PILE Muthambi side 27 27 0 0 0 0 0 0   Completed
2 PILE Thamarassery side 33 33 0 0 0 0 0 0   Completed
3 PILE NH SIDE 33 33 0 0 0 0 0 0   Completed
4 PILE CAP Muthambi SIDE 9 9 0 0 0 0 0 0   Completed
5 PILE CAP Thamarassery SIDE 11 11 0 0 0 0 0 0   Completed
6 PILE CAP NH SIDE 10 10 0 0 0 0 0 0   Completed
7 PIER Muthambi  SIDE 9 9 0 0 0 0 0 0   Completed
8 PIER Thamarassery SIDE 11 11 0 0 0 0 0 0   Completed
9 PIER NH SIDE 10 10 0 0 0 0 0 0   Completed
10 PIER CAP Muthambi  SIDE 9 9 0 0 0 0 0 0   Completed
11 PIER CAP Thamarassery SIDE 11 11 0 0 0 0 0 0   Completed
12 PIER CAP NH SIDE 10 10 0 0 0 0 0 0   Completed
13 RE/R WALL Muthambi side 100% 100% 0% 0 0.00% 0.00% 0 0.00%   Completed
14 RE/R WALL Thamarassery side SIDE 100% 94% 6% 0 6.00% 2.00% 0.04 4.00%   Hand rail work in progress
15 RE/R WALL NH SIDE 100% 100% 0% 0 0.00% 0.00% 0 0.00%    completed. 
16 BEAM/SLAB Muthambi SIDE 8 8 0 0 0 0 0 0   Completed
17 BEAM/SLAB Thamarassery SIDE 10 10 0 0 0 0 0 0   Completed
18 BEAM/SLAB NH SIDE 11 11 0 0 0 0 0 0   Completed
19 HR/FP/KERB Muthambi SIDE 100% 100% 0% 0 0.00% 0.00% 0 0.00%   Completed
20 HR/FP/KERB thamarassery SIDE 100% 100% 0% 0 0.00% 0.00% 0 0.00%   Completed
21 HR/FP/KERB NH SIDE 100% 100% 0% 0 0.00% 0.00% 0 0.00%   Completed
22 PAINTING 100% 80% 20% 0 20.00% 15.00% 0.05 5.00%   in progress. Only few touching works in balance
23 Mastic Work 100% 100% 0% 0 0.00% 0.00% 0 0.00%   Completed
23 Utility shifting             0     KSEB utility shifting started. Only 1 post remaining to shift 
                       
                       
                       
  Availbility of Men                     
  Date 23-03-13 24-03-13 25-03-13 26-03-13 27-03-13 28-03-13 29-03-13      
  Nof labours 40 28 35 38 32 25 25      
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) 40 45                
  Fine Aggreagate(m3) 30 25                
  Cement(bag) 500 500                
  Steel(MT) 15 20                
                       
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL                    
  KSEB                    
  KWA                    
  Others                    
                       
 
Back
 
    
WBM IN PROGRESS AT AP3 SIDE

    
    
T JUNCTION + RAILWAY SPAN

    
    
NH SIDE LONG VIEW

    
    
NH SIDE- APPROACH

    
 
    
COVER SLABS REPLACED AT NH SIDE

    
    
CLEANING WORK IN PROGRESS

    
    
AP3 SIDE LONG VIEW

    
 
    
AP2 SIDE SERVICE ROAD

    
    
AP2 SIDE LONG VIEW

    
    
AP2 APPROACH-BC WORK IN PROGRESS

    
 
 
 

 

 

 

 

 

 

 