PROGRESS OF RBDCK WORK AS ON 08.10.2010
  Description Completed/ Progress Remarks
  ROB Koratty    
  Approval of GAD by railways (Railway Portion) Approved Approved on 1-5-10
  Design and Drawing Submitted Approval pending with Railways
  Retaining wall concreting In progress  
  RE Wall work near Under Pass In progress   
 
Back
 
    
RE-WALL-TOWARDS-PULIKKAKKADAVU-SIDE-8.10.2010

    
    
RE-WALL-IN-THE-RHS-OF-BOX-UP-1

    
    
RCC-WALL-IN-THE-LHS-OF-BOX-UNDERPASS

    
    
END-OF-APPROACH-PORTION-TOWARDS-PULIKKAKKADAVU-SIDE-8.10.2010

    
 
    
RCC-WALL-TOWARDS-PULIKKAKKADAVU-SIDE-8.10.2010

      
 

 

 

 

 

 

 

 