Prevoius Weekly Reports

   Weekly Progress Report as on 22-03-2013
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 - - - - - -
4 PierCap 21 21 - - - - - -
5 Deck Slab 21 19 2 - - - - -
6 Hand Rails 21 19 2          
7 Expansion Joint 21 18 3   1 1 0 0
8 RC wall - Kuttipuram side 100% 78% 22% - 15% 5% 10% 15%
9 RC wall - Kanjipura side 100% 90% 10%   5% 5% 0% 5%
                   
                   
Date 16.03.13 18.03.13 19.03.13 20.03.13 21.03.13 22.03.13      
Climate Pleasant Pleasant Pleasant Pleasant Pleasant Pleasant      
No. of labours 30 30 30 30 30 30      
                   
                   
Availability of Materials                
                   
Material Required Available              
Fine aggregate 18 m3 20 m3              
Coarse Aggregate 28 m3  30 m3              
Cement 150 bags 200 bags              
Steel 15MT 20 MT              
 
Back
 
    
VIEW OF KUTTIPURAM SIDE

    
    
RC WALL AT KANJIPURA SIDE

    
    
BOX CULVERT WORK AT KUTTIPURAM SIDE

      
 

 

 

 

 

 

 

 