Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8053406
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly Progress Report as on 22-03-2013
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed    
2 PILE PADANNA SIDE 24 24 Completed    
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed    
4 PILE CAP  PADANNA SIDE 8 8 Completed    
5 PIER CHERUVATHOOR SIDE 9 9 Completed    
6 PIER PADANNA SIDE 8 8 Completed    
7 PIER CAP CHERUVATHOOR SIDE 9 9 Completed    
8 PIER CAP PADANNA SIDE 8 8 Completed    
9 RE/RC WALL CHERUVATHOOR  SIDE 100% 100% Completed   Friction slab and capping complete at both sides.
10 RE/RC  WALL PADANNA SIDE 100% 100% Completed   Friction slab capping complete at both RHS&LHS.
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 8 1 complete except railway adjacent span    
12 BEAM/SLAB PADANNA SIDE 8 7 1 complete except railway adjacent span    
13 EXPANSION JOINT CHERUVATHUR SIDE 9 8 1 0 0 0 0 0   complete except P8
14 EXPANSION JOINT PADANNA SIDE 8 6 2 1 1 1 0 0   complete except P7
15 KERB CHERUVATHOOR  SIDE 100% 100.00% Completed   complete for Friction slab also.
16 KERB PADANNA SIDE 100% 100% Completed   complete for RE Panel portion also.
17 HANDRAIL CHERUVATHUR SIDE 100% 100% Completed   complete for RE Panel portion also.
18 HANDRAIL PADANNA SIDE 100% 100% Completed   complete for RE Panel portion also.
17 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%   Painting to start this week,surface preparation works started.
18 Others/Miscellaneous                   Drainage works complete for 150 m at chr side.
19 ROAD WORK GSB+WMM Works resumed on 18.03.13   GSB+WMM complete for chr approach and for 4m service road (130m chr side),WMM IP for 7m road chr side.
                      Earth cutting in progress at Padanna side for both 7m and 4m roads
                      DR Work complete for 4m service road and 7m road.
                       
20 Deck Slab                    
21 Utility shifting                    
                       
                       
                       
  Availbility of Men                     
  Date 16-03-13 17-03-13 18-03-13 19-03-13 20-03-13 21-03-13 22-03-13      
  No of labours 8 2 8 8 8 8 8      
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) available                
  Fine Aggreagate(m3) available shortage of quarry dust for WMM Works.            
  Cement(bag) 50 70              
  Steel(MT) 0.5 1              
                       
 
Back
 
    
WMM AT CHERUVATHUR APPROACH

    
    
ROAD WORK AT CHERUVATHUR SIDE

    
    
EARTH CUTTING AT PADANNA SIDE FOR ROAD WORK

      
 

 

 

 

 

 

 

 

Untitled Document