   Weekly Progress Report as on 15.03.2013
    
 
Progress Report For Mooledam ROB for the week ending on 15-03-2013
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan
1 PILE 21 21 0 0 0 0 0 0 0
2 PILE CAP 7 7 0 0 0 0 0 0 0
3 PIER 9 8 1 0 1 0 1 1 0
4 PIER CAP 9 8 1 0 0 0 0 0 0
5 LOAD TEST 1 1 0 0 0 0 0 0 0
6 ABUTMENT 2 2 0 0 0 0 0 0 0
7 FOOTING 2 1 1 0 1 1 0 0 0
8 GIRDER 9 2 7 0 1 0 1 1 0
9 DECK SLAB 9 2 7 0 1 0 1 1 0
7 PEDESTAL 9 5 4 0 0 0 0 0 0
 
Back
 
    
ABUTMENT WALL A1

    
    
FOOTING P1 COMPLETED

    
    
DECK SLAB P3-P4 GETTING READY

      
 

 

 

 

 

 

 

 