Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7887830
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly Progress Report as on 01.03.2013
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 - - - - - -
4 PierCap 21 21 - - - - - -
5 Deck Slab 21 19 2 - - - - -
6 Hand Rails 21 19 2          
7 Expansion Joint 21 18 3   1 1 0 0
8 RC wall - Kuttipuram side 100% 60% 40% - 25% 18% 7% 25%
9 RC wall - Kanjipura side 100% 90% 10%   5% 5% 0% 5%
                   
Date 22.02.13 24.02.13 25.02.13 26.02.13 27.02.13 28.02.13      
Climate Pleasant Pleasant Pleasant Pleasant Pleasant Pleasant      
No. of labours 30 30 30 30 30 30      
                   
                   
Availability of Materials                
                   
Material Required Available              
Fine aggregate 14 m3 18 m3              
Coarse Aggregate 28 m3  32 m3              
Cement 180 bags 200 bags              
Steel 18 MT 24 MT              
 
Back
 
    
KUTTIPURAM SIDE VIEW

    
    
VIEW AT KUTTIPURAM SIDE

    
    
PCC WORK COMPLETED FOR BOX CULVERT AT KUTTIPURAM SIDE

      
 

 

 

 

 

 

 

 

Untitled Document