Prevoius Weekly Reports

   Weekly Progress Report as on 01.03.2013
    
Progress Report For Mooledam ROB for the month of February
Sl No  Activity Description  Total Quantity Cumulative progress upto last month  Balance  work up to last month Cumulative delay in Qty up to last month Work  planned  during the month  Actual work done during the month Cumulative delay in Qty up to this month Work  Planned for next month  No of days remaing for completion as per the weekly plan
1 PILE 21 21 0 0 0 0 0 0 0
2 PILE CAP 7 5 2 0 2 2 0 0 0
3 PIER 9 5 4 0 3 3 0 1 0
4 PIER CAP 9 5 4 0 3 1 2 3 0
5 LOAD TEST 1 1 0 0 0 0 0 0 0
6 ABUTMENT 2 1 1 0 0 0 0 1 0
7 FOOTING 2 0 2 0 2 1 1 1 0
8 GIRDER 9 0 9 0 2 2 0 2 0
9 DECK SLAB 9 0 9 0 2 2 0 2 0
10 RETAINING WALL 4 0 4 0 0 0 0 0.3 0
 
Back
 
    
PIERCAP P9 IN PROGRESS

    
    
PIERCAP P7 IN PROGRESS

    
    
DECK SLAB P4-P5 COMPLETED

    
    
ABUTMENT WALL CONCRETING IN PROGRESS

    
 
 
 

 

 

 

 

 

 

 