   Weekly Progress Report as on 22.02.2013
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE  CALICUT  SIDE 48 48 0 1 0 0 1 0    
2 PILE THIRUR SIDE 24 24 0 11 0 0 11 0    
3 PILE CAP CALICUT  SIDE 12 12 0 1 0 0 1 0    
4 PILE CAP  THIRURSIDE 6 6 0 5 0 0 5 0    
5 PIER CALICUT SIDE 12 12 0 1 0 0 1 0    
6 PIER THIRUR SIDE 6 6 0 1 0 0 1 0    
7 PIER CAPCALICUT   SIDE 12 12 0 2 0 0 2 0    
8 PIER CAP THIRUR SIDE 6 6 0 3 0 0 3 0    
9 RETAINING WALL WALL CALICUT   SIDE 100% 85.00% 15% 0 5.00% 5.00% 30.00% 5.00%    
10 RETAINING WALL THIRUR SIDE 100% 85% 15% 0 0.00% 0.00% 70.00% 0.00%    
11 BEAM CALICUT   SIDE 12 12 0 0 0 0 7 0    
12 SLAB CALICUT SIDE 12 11 1   1 0 10 1    
13 BEAM THIRUR SIDE 6 6 0 0 0 0 10 0    
14 SLAB TIRUR SIDE 6 6 1 0 0 0 2 0    
15 HR/FP/KERB CALICUT   SIDE 100% 95% 5% 0 0.00% 0.00% 10.00% 0.00%    
16 HR/FP/KERBTHIRUR SIDE 100% 80% 20% 0 10.00% 10.00% 55.00% 5.00%    
17 BC/PAINTING 100% 5% 95% 0 5.00% 5.00% 15.00% 15.00%   GSB started
18 Culvert calicut side 100% 100% 0% 0 0.00% 0.00% 30.00% 0.00%    
                       
                       
                       
  Availbility of Men                   
  Date 16-Feb-2013 17-Feb-2013 18-Feb-2013 19-Feb-2013 20-Feb-2013 21-Feb-2013 22-Feb-2013      
  Nof labours 17 17 17 17 17 17 17      
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3)       RMC            
  Fine Aggreagate(m3)                    
  Cement(bag)                    
  Steel(MT)                    
 
Back
 
    
BOULDER PACKING FOR APPROACH SLAB, TIRUR SIDE

    
    
GSB ON TIRUR SIDE

    
    
HANDRAILS & KERB WORKS IN PROGRESS @ TIRUR APPROACH SIDE

      
 

 

 

 

 

 

 

 