Progress Report For Cheruvathoor ROB for the week ending on 22-02-2013
|
|
Sl No
|
Activity Description
|
Total Quantity
|
Cumulative progress upto last week
|
Balance work up to last week
|
Cumulative delay in Qty up to last week
|
Work planned during the week
|
Actual work done during the week
|
Cumulative delay in Qty up to this week
|
Work Planned for next week
|
No of days remaing for completion as per the weekly plan
|
Remarks
|
1
|
PILE CHERUVATHOOR SIDE
|
27
|
27
|
Completed
|
|
|
2
|
PILE PADANNA SIDE
|
24
|
24
|
Completed
|
|
|
3
|
PILE CAP CHERUVATHOOR SIDE
|
9
|
9
|
Completed
|
|
|
4
|
PILE CAP PADANNA SIDE
|
8
|
8
|
Completed
|
|
|
5
|
PIER CHERUVATHOOR SIDE
|
9
|
9
|
Completed
|
|
|
6
|
PIER PADANNA SIDE
|
8
|
8
|
Completed
|
|
|
7
|
PIER CAP CHERUVATHOOR SIDE
|
9
|
9
|
Completed
|
|
|
8
|
PIER CAP PADANNA SIDE
|
8
|
8
|
Completed
|
|
|
9
|
RE/RC WALL CHERUVATHOOR SIDE
|
100%
|
100%
|
Completed
|
|
Friction slab and capping complete at both sides.
|
10
|
RE/RC WALL PADANNA SIDE
|
100%
|
100%
|
Completed
|
|
Friction slab capping complete at both RHS&LHS.
|
11
|
BEAM/SLAB CHERUVATHOOR SIDE
|
9
|
8
|
1
|
complete except railway adjacent span
|
|
|
12
|
BEAM/SLAB PADANNA SIDE
|
8
|
7
|
1
|
complete except railway adjacent span
|
|
|
13
|
EXPANSION JOINT CHERUVATHUR SIDE
|
9
|
8
|
1
|
0
|
0
|
0
|
0
|
0
|
|
complete except P8
|
14
|
EXPANSION JOINT PADANNA SIDE
|
8
|
6
|
2
|
1
|
1
|
0
|
1
|
1
|
|
AP1 Planned
|
15
|
KERB CHERUVATHOOR SIDE
|
100%
|
100.00%
|
Completed
|
|
complete for Friction slab also.
|
16
|
KERB PADANNA SIDE
|
100%
|
100%
|
Completed
|
|
complete for RE Panel portion also.
|
17
|
HANDRAIL CHERUVATHUR SIDE
|
100%
|
100%
|
Completed
|
|
complete for RE Panel portion also.
|
18
|
HANDRAIL PADANNA SIDE
|
100%
|
79%
|
21%
|
0%
|
10.00%
|
10.00%
|
0.00%
|
11.00%
|
|
RE Panel LHS complete
|
17
|
BC/PAINTING
|
100%
|
0
|
100%
|
0
|
0.00%
|
0.00%
|
0.00%
|
0.00%
|
|
Painting to start this week
|
18
|
Others/Miscellaneous
|
|
|
|
|
|
|
|
|
|
Drainage works complete for 150 m at chr side.
|
19
|
ROAD WORK
|
|
|
|
|
|
|
|
|
|
GSB+WMM complete for chr approach and for 4m service road (130m chr side),WMM IP for 7m road chr side.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
DR Work complete for 4m service road and 7m road.
|
|
|
|
|
|
|
|
|
|
|
|
|
20
|
Deck Slab
|
|
|
|
|
|
|
|
|
|
|
21
|
Utility shifting
|
|
|
|
|
|
|
|
|
|
|