Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8053904
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress report as on 22.02.2013
    

 

Progress Report For Cheruvathoor  ROB for the week ending on 22-02-2013

 

Sl No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

Remarks

1

PILE CHERUVATHOOR  SIDE

27

27

Completed

 

 

2

PILE PADANNA SIDE

24

24

Completed

 

 

3

PILE CAP CHERUVATHOOR SIDE

9

9

Completed

 

 

4

PILE CAP  PADANNA SIDE

8

8

Completed

 

 

5

PIER CHERUVATHOOR SIDE

9

9

Completed

 

 

6

PIER PADANNA SIDE

8

8

Completed

 

 

7

PIER CAP CHERUVATHOOR SIDE

9

9

Completed

 

 

8

PIER CAP PADANNA SIDE

8

8

Completed

 

 

9

RE/RC WALL CHERUVATHOOR  SIDE

100%

100%

Completed

 

Friction slab and capping complete at both sides.

10

RE/RC  WALL PADANNA SIDE

100%

100%

Completed

 

Friction slab capping complete at both RHS&LHS.

11

BEAM/SLAB CHERUVATHOOR  SIDE

9

8

1

complete except railway adjacent span

 

 

12

BEAM/SLAB PADANNA SIDE

8

7

1

complete except railway adjacent span

 

 

13

EXPANSION JOINT CHERUVATHUR SIDE

9

8

1

0

0

0

0

0

 

complete except P8

14

EXPANSION JOINT PADANNA SIDE

8

6

2

1

1

0

1

1

 

AP1 Planned

15

KERB CHERUVATHOOR  SIDE

100%

100.00%

Completed

 

complete for Friction slab also.

16

KERB PADANNA SIDE

100%

100%

Completed

 

complete for RE Panel portion also.

17

HANDRAIL CHERUVATHUR SIDE

100%

100%

Completed

 

complete for RE Panel portion also.

18

HANDRAIL PADANNA SIDE

100%

79%

21%

0%

10.00%

10.00%

0.00%

11.00%

 

RE Panel LHS complete

17

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

Painting to start this week

18

Others/Miscellaneous

 

 

 

 

 

 

 

 

 

Drainage works complete for 150 m at chr side.

19

ROAD WORK

 

 

 

 

 

 

 

 

 

GSB+WMM complete for chr approach and for 4m service road (130m chr side),WMM IP for 7m road chr side.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

DR Work complete for 4m service road and 7m road.

 

 

 

 

 

 

 

 

 

 

 

 

20

Deck Slab

 

 

 

 

 

 

 

 

 

 

21

Utility shifting

 

 

 

 

 

 

 

 

 

 

 
Back
 
    
WMM COMPLETE ON CHERUVATHUR APPROACH PORTION

    
    
HAND RAIL CONCRETING ON PADANNA SIDE

      
 

 

 

 

 

 

 

 

Untitled Document