Prevoius Weekly Reports

   Weekly progress report as on 22.02.2013
    

 

Revised Progress Report For Ponnurunni ROB for the week ending on 21.02.13

Si No

Activity Description

Total Quantity

Cumulative progress upto 21.02.13

Balance  work up to 21.02.13

Cumulative delay in Qty up to 21.02.13

Work  planned  during the week

Actual work done during the week

delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

Remarks

1

PILE  Palarivattom side(Approach portion)

31

31

0

0

0

0

0

0

completed

 

2

PILE Palarivattom side(railway portion)

6

6

0

0

0

0

0

0

3

PILE vytilla side(Approach portion)

42

42

0

0

0

0

0

0

completed

 

4

PILE vytilla side(railway portion)

6

6

0

0

0

0

0

0

5

PILE CAP Palarivattom side(Approach portion)

8

8

0

0

0

0

0

0

completed

P15, P14, A2, P13, P12, P11, P10, P9

6

PILE CAP Palarivattom side(railway portion)

1

1

0

0

0

0

0

0

completed

RP2

7

PILE CAP vytilla side(Approach portion)

9

9

0

0

0

0

0

0

completed

P1,  P2, P4, P3, A1, P5,P6, P7,P8

8

PILE CAP vytilla side(railway portion)

1

1

0

0

0

0

0

0

completed

RP1

9

PIER Palarivattom side(Approach portion)

8

8

0

0

0

0

0

0

completed

A2, P15, P14, P13,  P12,  P11, P10, P9

10

PIER Palarivattomside(railway portion)

1

1

0

0

0

0

0

0

completed

RP2

11

PIER Vytilla side(Approach portion)

9

9

0

0

0

0

0

0

completed

P1, P2, P3, P4, A1,P5,P6,P7, P8

12

PIER vytilla side(railway portion)

1

1

0

0

0

0

0

0

completed

RP1

13

PIER  CAP Palarivattom side(Approach portion)

8

8

0

0

0

0

0

0

completed

P15, P14, A2, P13, P12, P11, P10, P9

14

PIER  CAP Vytila side(Approach portion)

9

9

0

0

0

0

0

0

completed

P1, P2, P3, A1,P4,P5,P6,P7, P8

15

GIRDER Palarivattom side(Approach portion)

8

8

0

0

0

0

0

0

completed

A2 P15,P15 P14,P14 P13, P13 P12, P11 P10, P12 P11, P10P9, P9RP2

16

GIRDER Vytila side(Approach portion)

9

8

1

0

0

0

0

0

 

P1P2,  A1P1, P2P3, P3P4, P5P6, P6P7, P4P5, P7P8

17

DECK SLAB Palarivattom side(Approach portion)

8

8

0

0

0

0

0

0

completed

A2 P15, P15 P14, P14 P13,  P13 P12, P11P10, P12 P11, P10P9, P9RP2

18

DECK SLABVytila side(Approach portion)

9

8

1

0

0

0

0

0

 

P1P2,A1P1, P2P3, P3P4, P4P5, P5P6, P6P7, P7P8

19

PIER CAP Palarivattomside(railway portion)

1

1

0

0

0

0

0

0

completed

RP2

20

PIER CAP vytilla side(railway portion)

1

1

0

0

0

0

0

0

completed

RP1

21

RE WALL PANEL CASTING

351

351

0

0

0

0

0

0

completed

 

20

RE WALL PCC Palarivattom

95

95

0

0

0

0

0

0

completed

 

21

RE WALL Panel erection Palarivattom

100%

100%

0

0

100%

10%

0%

100%

completed

 

21

RE WALL Earth filling PALARIVATTOM

100%

100%

0

0

100%

0%

0%

0%

 

 

22

RE Wall finishing

100%

30%

0.7

0

5%

20%

0%

25%

 

 

23

Rly Pile Load test

1

1

0

0

1

1

0

0

completed

 

 