Revised Progress Report For Ponnurunni ROB for the week ending on 21.02.13
|
Si No
|
Activity Description
|
Total Quantity
|
Cumulative progress upto 21.02.13
|
Balance work up to 21.02.13
|
Cumulative delay in Qty up to 21.02.13
|
Work planned during the week
|
Actual work done during the week
|
delay in Qty up to this week
|
Work Planned for next week
|
No of days remaing for completion as per the weekly plan
|
Remarks
|
1
|
PILE Palarivattom side(Approach portion)
|
31
|
31
|
0
|
0
|
0
|
0
|
0
|
0
|
completed
|
|
2
|
PILE Palarivattom side(railway portion)
|
6
|
6
|
0
|
0
|
0
|
0
|
0
|
0
|
3
|
PILE vytilla side(Approach portion)
|
42
|
42
|
0
|
0
|
0
|
0
|
0
|
0
|
completed
|
|
4
|
PILE vytilla side(railway portion)
|
6
|
6
|
0
|
0
|
0
|
0
|
0
|
0
|
5
|
PILE CAP Palarivattom side(Approach portion)
|
8
|
8
|
0
|
0
|
0
|
0
|
0
|
0
|
completed
|
P15, P14, A2, P13, P12, P11, P10, P9
|
6
|
PILE CAP Palarivattom side(railway portion)
|
1
|
1
|
0
|
0
|
0
|
0
|
0
|
0
|
completed
|
RP2
|
7
|
PILE CAP vytilla side(Approach portion)
|
9
|
9
|
0
|
0
|
0
|
0
|
0
|
0
|
completed
|
P1, P2, P4, P3, A1, P5,P6, P7,P8
|
8
|
PILE CAP vytilla side(railway portion)
|
1
|
1
|
0
|
0
|
0
|
0
|
0
|
0
|
completed
|
RP1
|
9
|
PIER Palarivattom side(Approach portion)
|
8
|
8
|
0
|
0
|
0
|
0
|
0
|
0
|
completed
|
A2, P15, P14, P13, P12, P11, P10, P9
|
10
|
PIER Palarivattomside(railway portion)
|
1
|
1
|
0
|
0
|
0
|
0
|
0
|
0
|
completed
|
RP2
|
11
|
PIER Vytilla side(Approach portion)
|
9
|
9
|
0
|
0
|
0
|
0
|
0
|
0
|
completed
|
P1, P2, P3, P4, A1,P5,P6,P7, P8
|
12
|
PIER vytilla side(railway portion)
|
1
|
1
|
0
|
0
|
0
|
0
|
0
|
0
|
completed
|
RP1
|
13
|
PIER CAP Palarivattom side(Approach portion)
|
8
|
8
|
0
|
0
|
0
|
0
|
0
|
0
|
completed
|
P15, P14, A2, P13, P12, P11, P10, P9
|
14
|
PIER CAP Vytila side(Approach portion)
|
9
|
9
|
0
|
0
|
0
|
0
|
0
|
0
|
completed
|
P1, P2, P3, A1,P4,P5,P6,P7, P8
|
15
|
GIRDER Palarivattom side(Approach portion)
|
8
|
8
|
0
|
0
|
0
|
0
|
0
|
0
|
completed
|
A2 P15,P15 P14,P14 P13, P13 P12, P11 P10, P12 P11, P10P9, P9RP2
|
16
|
GIRDER Vytila side(Approach portion)
|
9
|
8
|
1
|
0
|
0
|
0
|
0
|
0
|
|
P1P2, A1P1, P2P3, P3P4, P5P6, P6P7, P4P5, P7P8
|
17
|
DECK SLAB Palarivattom side(Approach portion)
|
8
|
8
|
0
|
0
|
0
|
0
|
0
|
0
|
completed
|
A2 P15, P15 P14, P14 P13, P13 P12, P11P10, P12 P11, P10P9, P9RP2
|
18
|
DECK SLABVytila side(Approach portion)
|
9
|
8
|
1
|
0
|
0
|
0
|
0
|
0
|
|
P1P2,A1P1, P2P3, P3P4, P4P5, P5P6, P6P7, P7P8
|
19
|
PIER CAP Palarivattomside(railway portion)
|
1
|
1
|
0
|
0
|
0
|
0
|
0
|
0
|
completed
|
RP2
|
20
|
PIER CAP vytilla side(railway portion)
|
1
|
1
|
0
|
0
|
0
|
0
|
0
|
0
|
completed
|
RP1
|
21
|
RE WALL PANEL CASTING
|
351
|
351
|
0
|
0
|
0
|
0
|
0
|
0
|
completed
|
|
20
|
RE WALL PCC Palarivattom
|
95
|
95
|
0
|
0
|
0
|
0
|
0
|
0
|
completed
|
|
21
|
RE WALL Panel erection Palarivattom
|
100%
|
100%
|
0
|
0
|
100%
|
10%
|
0%
|
100%
|
completed
|
|
21
|
RE WALL Earth filling PALARIVATTOM
|
100%
|
100%
|
0
|
0
|
100%
|
0%
|
0%
|
0%
|
|
|
22
|
RE Wall finishing
|
100%
|
30%
|
0.7
|
0
|
5%
|
20%
|
0%
|
25%
|
|
|
23
|
Rly Pile Load test
|
1
|
1
|
0
|
0
|
1
|
1
|
0
|
0
|
completed
|
|