   Weekly progress report as on 22.02.2013
    

 

Progress Report - ROB-Thirunavaya   -22.02.2013

Sl.No

Activity Description

Total Quantity

Cumulative Progress upto last week

Balance work up to last week

Cumulative delay in Qty up to last week

Work planned during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work planned for the next week

1

Piles

63

63

-

-

-

-

-

-

2

Pile cap

21

21

-

-

-

-

-

-

3

Pier

21

21

-

-

-

-

-

-

4

PierCap

21

21

-

-

-

-

-

-

5

Deck Slab

21

19

2

-

-

-

-

-

6

Hand Rails

21

19

2

 

 

 

 

 

7

Expansion Joint

21

19

2

 

0

0

0

0

8

RC wall - Kuttipuram side

100%

45%

55%

-

25%

10%

15%

15%

9

RC wall - Kanjipura side

100%

90%

10%

 

5%

0%

5%

5%

 

 

 

 

 

 

 

 

 

 

Date

16.02.13

18.02.13

19.02.13

20.02.13

21.02.13

22.02.13

 

 

 

Climate

Pleasant

Pleasant

Pleasant

Pleasant

Pleasant

Pleasant

 

 

 

No. of labours

25

25

25

25

25

25

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Availability of Materials

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Material

Required

Available

 

 

 

 

 

 

 

Fine aggregate

26 m3

15 m3

 

 

 

 

 

 

 

Coarse Aggregate

52 m3

20 m3

 

 

 

 

 

 

 

Cement

500 Bags

320 Bags

 

 

 

 

 

 

 

Steel

5 MT

3MT

 

 

 

 

 

 

 

 
Back
 
    
AP2 SIDE EARTH FILLING

    
    
AP1 SIDE RAFT CONCRETING

    
    