   Weekly progress report as on 22.02.2013
    

1. Stanchion erection for the centre span has been completed.

2. staging erection will be completed by february 2013.

3. Parapet wall works of adjacent spans will be completed by february 2013

 
Back
 
    
STANCHION ERECTED FOR CENTRE SPAN

    
    
STANCHION ERECTION ON DOWNLINE SIDE

    
    
STANCHION ERECTION ON UPLINE SIDE

      
 

 

 

 

 

 

 

 