Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7886926
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress report as on 15.2.2012
    

 

Progress Report For Anayara ROB for the week ending on 15.2.2013      
                   
Sl No  Activity Description  Total Quantity Cumulative progress upto 15.2.2013 Balance  work up to 15.2.2013 Cumulative delay in Qty up to 15.2.2013 Work  planned  during the week  Actual work done during the week  Delay in Qty up to this week Work  Planned for next week 
1 PILE  Pettah side(Approach portion) 12 12 0 0 0 0 0 0
2 PILE Anayara side(Approach portion) 12 12 0 0 0 0 0 0
3 PILE CAP Pettah side(Approach portion) 4 4 0 0 0 0 0 0
4 PILE CAP Anayara side(Approach portion) 4 4 0 0 0 0 0 0
5 PIER Pettah side(Approach portion) 4 4 0 0 0 0 0 0
6 PIER Anayara side(Approach portion) 4 4 0 0 0 0 0 0
7 PIER  CAP Pettah side(Approach portion) 4 4 0 0 0 0 0 0
  PIER  CAP Anayara side(Approach portion) 4 4 0 0 0 0 0 0
8 GIRDER Pettah side(Approach portion) 4 3 1          
9 GIRDER Anayara side(Approach portion) 4 3 1          
10 Service Road Pettah side(Approach portion) 1400 350 1050          
11 Service Road Anayara side(Approach portion) 1400 350 1050          
12 RT Wall Pettah side(Approach portion) % 100 100 0          
13 RT Wall Anayara side(Approach portion) % 100 100 0                
14 RE Wall Panel Casting Pettah side(Approach portion) 400 400 0          
15 RE Wall Panel Casting Anayara side(Approach portion) 400 400 0          
16 RE Wall Panel Erection Pettah side(Approach portion) 400 400 0          
17 RE Wall Panel Erection Anayara side(Approach portion) 400 400 0          
18 Expansion Joint(Pettah side) 4 3 1          
19 Expansion Joint(Anayara side) 4 3 1          
20 Friction Slab   (Pettah side) 2 2 0          
21 Friction Slab(Anayara side) 2 2 0          
 
Back
 
    
SERVICE ROAD AT PETTA SIDE

    
    
SERVICE ROAD AT ANAYARA SIDE

    
    
GIRDER RP4-P4.

    
    
APPROACH AT ANAYARA SIDE

    
 
 
 

 

 

 

 

 

 

 

Untitled Document