   Weekly report as on 15.02.2013
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaining for completion as per the weekly plan Remarks 
1 PILE Muthambi side 27 27 0 0 0 0 0 0   Completed
2 PILE Thamarassery side 33 33 0 0 0 0 0 0   Completed
3 PILE NH SIDE 33 33 0 0 0 0 0 0   Completed
4 PILE CAP Muthambi SIDE 9 9 0 0 0 0 0 0   Completed
5 PILE CAP Thamarassery SIDE 11 11 0 0 0 0 0 0   Completed
6 PILE CAP NH SIDE 10 10 0 0 0 0 0 0   Completed
7 PIER Muthambi  SIDE 9 9 0 0 0 0 0 0   Completed
8 PIER Thamarassery SIDE 11 11 0 0 0 0 0 0   Completed
9 PIER NH SIDE 10 10 0 0 0 0 0 0   Completed
10 PIER CAP Muthambi  SIDE 9 9 0 0 0 0 0 0   Completed
11 PIER CAP Thamarassery SIDE 11 11 0 0 0 0 0 0   Completed
12 PIER CAP NH SIDE 10 10 0 0 0 0 0 0   Completed
13 RE/R WALL Muthambi side 100% 95% 5% 0 5.00% 0.00% 0.05 5.00%   Only Hand rail work pending
14 RE/R WALL Thamarassery side SIDE 100% 80% 20% 0 10.00% 5.00% 0.05 10.00%   Side Wall work in progress
15 RE/R WALL NH SIDE 100% 100% 0% 0 0.00% 0.00% 0 0.00%    completed. 
16 BEAM/SLAB Muthambi SIDE 8 8 0 0 0 0 0 0   Completed
17 BEAM/SLAB Thamarassery SIDE 10 10 0 0 0 0 0 0   Completed
18 BEAM/SLAB NH SIDE 11 11 0 0 0 0 0 0   Completed
19 HR/FP/KERB Muthambi SIDE 100% 100% 0% 0 0.00% 0.00% 0 0.00%   Completed
20 HR/FP/KERB thamarassery SIDE 100% 100% 0% 0 0.00% 0.00% 0 0.00%   Completed
21 HR/FP/KERB NH SIDE 100% 100% 0% 0 0.00% 0.00% 0 0.00%   Completed
22 PAINTING 100% 0 100% 0 10.00% 10.00% 0 20.00%   IN progress
23 Utility shifting             0     KSEB utility shifting started. Only 1 post remaining to shift 
                       
                       
                       
  Availbility of Men                     
  Date 09-02-13 10-02-13 11-02-13 12-02-13 13-02-13 14-02-13 15-02-13      
  Nof labours 42 36 44 46 46 43 43      
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) 40 45                
  Fine Aggreagate(m3) 30 20                
  Cement(bag) 600 100                
  Steel(MT) 20 25                
                       
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL                    
  KSEB                    
  KWA                    
  Others                    
                       
 
Back
 
    
PAINTING WORK IN PROGRESS NH SIDE

    
    
NH SIDE WBM IN FINAL STAGE

    
    
MASTIC WORK AP2 SIDE

    
    
DRAIN WORK NH SIDE

    
 
    
AP2 SIDE LONG VIEW

    
    
AP2 SIDE APPROACH

      
 

 

 

 

 

 

 

 

Untitled Document