   Weekly report as on 01.02.2013
    

 


Road to Prosperity
Site last updated on:  08-02-2013 | You are visitor: 284508
Completed Projects Weekly Progress Citizen Charter Project in the offing Citizen Services Careers Archives


rbdckadmin

Weekly Reports

 
 

ROB at Quilandy -Manager in Charge-Tinu Davis

Graph Project Graph

Weekly progress report as on 04-01-2013
 
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaining for completion as per the weekly plan Remarks 
1 PILE Muthambi side 27 27 0 0 0 0 0 0   Completed
2 PILE Thamarassery side 33 33 0 0 0 0 0 0   Completed
3 PILE NH SIDE 33 33 0 0 0 0 0 0   Completed
4 PILE CAP Muthambi SIDE 9 9 0 0 0 0 0 0   Completed
5 PILE CAP Thamarassery SIDE 11 11 0 0 0 0 0 0   Completed
6 PILE CAP NH SIDE 10 10 0 0 0 0 0 0   Completed
7 PIER Muthambi  SIDE 9 9 0 0 0 0 0 0   Completed
8 PIER Thamarassery SIDE 11 11 0 0 0 0 0 0   Completed
9 PIER NH SIDE 10 10 0 0 0 0 0 0   Completed
10 PIER CAP Muthambi  SIDE 9 9 0 0 0 0 0 0   Completed
11 PIER CAP Thamarassery SIDE 11 11 0 0 0 0 0 0   Completed
12 PIER CAP NH SIDE 10 10 0 0 0 0 0 0   Completed
13 RE/R WALL Muthambi side 100% 65% 35% 0 20.00% 10.00% 0.1 15.00%   Side wall and haunch work in progress
14 RE/R WALL Thamarassery side SIDE 100% 70% 30% 0 15.00% 0.00% 0.15 15.00%   LA issue solved. Work resumed
15 RE/R WALL NH SIDE 100% 100% 0% 0 0.00% 0.00% 0 0.00%    completed. 
16 BEAM/SLAB Muthambi SIDE 8 8 0 0 0 0 0 0   Completed
17 BEAM/SLAB Thamarassery SIDE 10 10 0 0 0 0 0 0   Completed
18 BEAM/SLAB NH SIDE 11 10 1 0 1 0 1 1 5 P8-P9 completed.                 P7-RP2 work in progress
19 HR/FP/KERB Muthambi SIDE 100% 85% 15% 0 0.00% 0.00% 0 15.00%   Kerb casting&Hand rail fixing in progress
20 HR/FP/KERB thamarassery SIDE 100% 85% 15% 0 0.00% 0.00% 0 15.00%   Kerb casting&Hand rail fixing in progress
21 HR/FP/KERB NH SIDE 100% 75% 25% 0 0.00% 0.00% 0 0.00%   Kerb casting&Hand rail fixing in progress
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0 0.00%    
23 Utility shifting             0     KSEB utility shifting started. Only 1 post remaining to shift 
                       
                       
                       
  Availbility of Men                     
  Date   29-12-2012 30-12-2012 31-12-2012 01-01-2013 02-01-2013 03-01-2013 04-01-2013    
  Nof labours   40 24 43 43 45 42 42    
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) 55 60                
  Fine Aggreagate(m3) 55 60                
  Cement(bag) 750 200                
  Steel(MT) 25 35                
                       
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL                    
  KSEB                    
  KWA                    
  Others                    
 
 