Prevoius Weekly Reports
|
18.05.2010 |
|
ROB at Bakel
PROGRESS OF ROB WORK AS ON 15.05.2010 |
Work Planned upto 15/05/2010 |
Completed / Progress |
Span of Kasargod side |
|
Staging work |
Completed |
Bar bending |
In progress |
Beam side shuttering 3rd beam |
In progress |
Bar fixing - for 3rd beam |
Completed |
Concreting beam 2 Nos. |
Completed |
|
|
Back |
|
No images are uploaded for this Weekly Reports
|
|
|