18.05.2010 |
| |
ROB at Bakel
|
PROGRESS OF ROB WORK AS ON 15.05.2010 |
|
Work Planned upto 15/05/2010 |
Completed / Progress |
|
Span of Kasargod side |
|
|
Staging work |
Completed |
|
Bar bending |
In progress |
|
Beam side shuttering 3rd beam |
In progress |
|
Bar fixing - for 3rd beam |
Completed |
|
Concreting beam 2 Nos. |
Completed |
|
| |