Prevoius Weekly Reports

   weekly progress as on 1.2.2013
    
ROB at Parappanangady    
Pier cap (Total no of pier Cap- 21) Completed 21 NOS COMPLETED
RE Wall panel casting ( total600 nos) Completed Errection completed.
Slab calicut side  (total 10 nos ) Completed  10 nos, adjacent span completed.
slab NH side ( 11 nos) Completed  11 nos,adjacent span completed.
Retaining wall NH side completed completed
Retaining wall calicut side completed  completed
Dirt wall AP2 concreting  completed Done 100%
Dirt wall AP1 concreting  completed Done 100%
Handrail casting & fixing. completed  completed.
Adjacent span RP1-P9 completed completed.
Adjacent span RP4-P10 completed completed.
NH side RE panel errection completed 100% completed.
RE wall work calicut side. completed 100% completed.
expansion joint  completed completed.
painting-slab completed Existing structures completed (adjacent span balance ).
Road tarring work. completed NH-side completed,calicut side approach road not completed.
RAILWAY PORTION    
Pilling work  Completed piling completed.
 RP1 In progress pier ,piercap completed.
 RP2 In progress pier & piercap completed.
 RP3 In progress pier & piercap completed.
 RP3 In progress pier &piercap completed.
TEMPERORY STAGING-CENTER SPAN Completed Girder reinforcement work in progress.
CENTER SPAN In progress slab reinforcement completed,concreted.
STAGING In progress RP3-RP4 span girder reinforcement started.
 