ROB at Parappanangady |
|
|
Pier cap (Total no of pier Cap- 21) |
Completed |
21 NOS COMPLETED |
RE Wall panel casting ( total600 nos) |
Completed |
Errection completed. |
Slab calicut side (total 10 nos ) |
Completed |
10 nos, adjacent span completed. |
slab NH side ( 11 nos) |
Completed |
11 nos,adjacent span completed. |
Retaining wall NH side |
completed |
completed |
Retaining wall calicut side |
completed |
completed |
Dirt wall AP2 concreting |
completed |
Done 100% |
Dirt wall AP1 concreting |
completed |
Done 100% |
Handrail casting & fixing. |
completed |
completed. |
Adjacent span RP1-P9 |
completed |
completed. |
Adjacent span RP4-P10 |
completed |
completed. |
NH side RE panel errection |
completed |
100% completed. |
RE wall work calicut side. |
completed |
100% completed. |
expansion joint |
completed |
completed. |
painting-slab |
completed |
Existing structures completed (adjacent span balance ). |
Road tarring work. |
completed |
NH-side completed,calicut side approach road not completed. |
RAILWAY PORTION |
|
|
Pilling work |
Completed |
piling completed. |
RP1 |
In progress |
pier ,piercap completed. |
RP2 |
In progress |
pier & piercap completed. |
RP3 |
In progress |
pier & piercap completed. |
RP3 |
In progress |
pier &piercap completed. |
TEMPERORY STAGING-CENTER SPAN |
Completed |
Girder reinforcement work in progress. |
CENTER SPAN |
In progress |
slab reinforcement completed,concreted. |
STAGING |
In progress |
RP3-RP4 span girder reinforcement started. |