Sl No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
No of days remaing for completion as per the weekly plan |
Remarks |
1 |
PILE CHERUVATHOOR SIDE |
27 |
27 |
Completed |
|
|
2 |
PILE PADANNA SIDE |
24 |
24 |
Completed |
|
|
3 |
PILE CAP CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
|
4 |
PILE CAP PADANNA SIDE |
8 |
8 |
Completed |
|
|
5 |
PIER CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
|
6 |
PIER PADANNA SIDE |
8 |
8 |
Completed |
|
|
7 |
PIER CAP CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
|
8 |
PIER CAP PADANNA SIDE |
8 |
8 |
Completed |
|
|
9 |
RE/RC WALL CHERUVATHOOR SIDE |
100% |
100% |
Completed |
|
Friction slab and capping complete at both sides. |
10 |
RE/RC WALL PADANNA SIDE |
100% |
94% |
6% |
5% |
5.00% |
1.00% |
4.00% |
2.00% |
|
Friction slab capping complete for 20m at RHS. |
11 |
BEAM/SLAB CHERUVATHOOR SIDE |
9 |
8 |
1 |
complete except railway adjacent span |
|
|
12 |
BEAM/SLAB PADANNA SIDE |
8 |
7 |
1 |
complete except railway adjacent span |
|
|
13 |
EXPANSION JOINT CHERUVATHUR SIDE |
9 |
8 |
1 |
0 |
0 |
0 |
0 |
0 |
|
complete except P8 |
14 |
EXPANSION JOINT PADANNA SIDE |
8 |
6 |
2 |
1 |
1 |
0 |
1 |
1 |
|
AP1 Planned |
15 |
KERB CHERUVATHOOR SIDE |
100% |
100.00% |
Completed |
|
complete for Friction slab also. |
16 |
KERB PADANNA SIDE |
100% |
80% |
20% |
0 |
10.00% |
5.00% |
5.00% |
10.00% |
|
complete for 20m at RHS. |
17 |
HANDRAIL CHERUVATHUR SIDE |
100% |
100% |
Completed |
|
complete for RE Panel portion also. |
18 |
HANDRAIL PADANNA SIDE |
100% |
79% |
21% |
0% |
0.00% |
0.00% |
0.00% |
0.00% |
|
RE Panel portion remaining |
17 |
BC/PAINTING |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
Grinding and finishing works in progress at both sides. |
18 |
Others/Miscellaneous |
|
|
|
|
|
|
|
|
|
Drainage works complete for 100 m at chr side.DRAINAGE INFRONT OF UNITY HOSPITAL complete. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
DR Work complete for 4m service road and 7m road. |