Prevoius Weekly Reports

   Weekly Progress Report as on 18.01.2013
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 - - - - - -
4 PierCap 21 21 - - - - - -
5 Deck Slab 21 19 2 - - - - -
6 Hand Rails 21 15 6   2 1 1 2
7 Expansion Joint 21 18 3   2 0 2 2
8 RC wall - Kuttipuram side 100% 25% 75% - 0% 0% 0% 0%
9 RC wall - Kanjipura side 100% 60% 40%   25% 10% 15% 25%
                   
Date 12.01.13 14.01.13 15.01.13 16.01.13 17.01.13 18.01.13      
Climate Pleasant Pleasant Pleasant Pleasant Pleasant Pleasant      
No. of labours 35 30 30 30 30 30      
                   
                   
Availability of Materials                
                   
Material Required Available              
Fine aggregate 20 m3 3 m3 Tipper strike            
Coarse Aggregate 18 m3  4 m3 Tipper strike            
Cement 250 bags 320 bags              
Steel 8 MT 16 MT              
 