Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8053459
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly Progress Report as on 18.01.2013
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed    
2 PILE PADANNA SIDE 24 24 Completed    
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed    
4 PILE CAP  PADANNA SIDE 8 8 Completed    
5 PIER CHERUVATHOOR SIDE 9 9 Completed    
6 PIER PADANNA SIDE 8 8 Completed    
7 PIER CAP CHERUVATHOOR SIDE 9 9 Completed    
8 PIER CAP PADANNA SIDE 8 8 Completed    
9 RE/RC WALL CHERUVATHOOR  SIDE 100% 100% Completed   Friction slab and capping complete at both sides.
10 RE/RC  WALL PADANNA SIDE 100% 91% 9% 5% 5.00% 3.00% 2.00% 5.00%   Friction slab complete except kerb portion.
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 8 1 complete except railway adjacent span    
12 BEAM/SLAB PADANNA SIDE 8 7 1 complete except railway adjacent span    
13 EXPANSION JOINT CHERUVATHUR SIDE 9 8 1 0 0 0 0 0   complete except P8
14 EXPANSION JOINT PADANNA SIDE 8 6 2 1 1 0 1 1   AP1 Planned
15 KERB CHERUVATHOOR  SIDE 100% 100.00% Completed   complete for Friction slab also.
16 KERB PADANNA SIDE 100% 80% 20% 0 0.00% 0.00% 0.00% 10.00%   RE Panel portion remaining
17 HANDRAIL CHERUVATHUR SIDE 100% 100% Completed   complete for RE Panel portion also.
18 HANDRAIL PADANNA SIDE 100% 79% 21% 0% 0.00% 0.00% 0.00% 0.00%   RE Panel portion remaining
17 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%   Grinding and finishing works in progress at both sides.
18 Others/Miscellaneous                   Drainage works complete for 100 m at chr side.DRAINAGE INFRONT OF UNITY HOSPITAL complete.
                       
                       
                      DR Work complete for 4m service road and 7m road.
                       
19 Deck Slab                    
20 Utility shifting                    
                       
                       
                       
  Availbility of Men                     
  Date 01-12-13 13/1/13 14/1/13 15/1/13 16/1/13 17/1/13 18/1/13      
  No of labours 23 12 23 23 23 16 21      
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) available                
  Fine Aggreagate(m3) available                
  Cement(bag) 100 200              
  Steel(MT) 2 4              
 
Back
 
    
FRICTION SLAB CONCRETE

    
    
ELECTRIC POST INFRONT OF UNITY HOSPITAL-SHIFTING IP

    
    
DRAINAGE COVER SLAB CASTING IP

      
 

 

 

 

 

 

 

 

Untitled Document