   weekly report as on 11.1.2013
    

 


Sl No Activity Description  Total Quantity Cumulative progress upto 11.1.2013 Balance  work up to 11.1.2013 Cumulative delay in Qty up to 11.1.2013 Work  planned during the week  Actual work done during the week  Delay in Qty up to this week Work  Planned for next week 
1 PILE  Pettah side(Approach portion) 12 12 0 0 0 0 0 0
2 PILE Anayara side(Approach portion) 12 12 0 0 0 0 0 0
3 PILE CAP Pettah side(Approach portion) 4 4 0 0 0 0 0 0
4 PILE CAP Anayara side(Approach portion) 4 4 0 0 0 0 0 0
5 PIER Pettah side(Approach portion) 4 4 0 0 0 0 0 0
6 PIER Anayara side(Approach portion) 4 4 0 0 0 0 0 0
7 PIER  CAP Pettah side(Approach portion) 4 4 0 0 0 0 0 0
  PIER  CAP Anayara side(Approach portion) 4 4 0 0 0 0 0 0
8 GIRDER Pettah side(Approach portion) 4 3 1          
9 GIRDER Anayara side(Approach portion) 4 3 1          
10 Service Road Pettah side(Approach portion) 1400 350 1050          
11 Service Road Anayara side(Approach portion) 1400 350 1050          
12 RT Wall Pettah side(Approach portion) % 100 100 0          
13 RT Wall Anayara side(Approach portion) % 100 100 0                
14 RE Wall Panel Casting Pettah side(Approach portion) 400 400 0          
15 RE Wall Panel Casting Anayara side(Approach portion) 400 400 0          
16 RE Wall Panel Erection Pettah side(Approach portion) 400 400 0          
17 RE Wall Panel Erection Anayara side(Approach portion) 400 400 0          
18 Expansion Joint(Pettah side) 4 3 1          
19 Expansion Joint(Anayara side) 4 3 1          
20 Friction Slab   (Pettah side) 2 2 0          
21 Friction Slab(Anayara side) 2 2 0          
 