   weekly progress report as on 11.1.2013
    

 

 

 

Sl No Activity Description Total Quantity Cumulative progress upto 28.12.12 Balance work up to 28.12.12 Cumulative delay in Qty up to 28.12.12 Work planned during the week Actual work done during the week Delay in Qty up to this week Work Planned for next week
1 PILE Pettah side(Approach portion) 12 12 0 0 0 0 0 0
2 PILE Anayara side(Approach portion) 12 12 0 0 0 0 0 0
3 PILE CAP Pettah side(Approach portion) 4 4 0 0 0 0 0 0
4 PILE CAP Anayara side(Approach portion) 4 4 0 0 0 0 0 0
5 PIER Pettah side(Approach portion) 4 4 0 0 0 0 0 0
6 PIER Anayara side(Approach portion) 4 4 0 0 0 0 0 0
7 PIER CAP Pettah side(Approach portion) 4 4 0 0 0 0 0 0
  PIER CAP Anayara side(Approach portion) 4 4 0 0 0 0 0 0
8 GIRDER Pettah side(Approach portion) 4 3 1          
9 GIRDER Anayara side(Approach portion) 4 3 1          
10 Service Road Pettah side(Approach portion) 1400 350 1050          
11 Service Road Anayara side(Approach portion) 1400 350 1050          
12 RT Wall Pettah side(Approach portion) % 100 100 0          
13 RT Wall Anayara side(Approach portion) % 100 100 0          
14 RE Wall Panel Casting Pettah side(Approach portion) 400 400 0          
15 RE Wall Panel Casting Anayara side(Approach portion) 400 400 0          
16 RE Wall Panel Erection Pettah side(Approach portion) 400 400 0          
17 RE Wall Panel Erection Anayara side(Approach portion) 400 400 0          
18 Expansion Joint(Pettah side) 4 3 1          
19 Expansion Joint(Anayara side) 4 3 1          
20 Friction Slab (Pettah side) 2 2 0          
21 Friction Slab(Anayara side) 2 2 0          
 