|
ROB at Sulthanpet - Palaghat Town |
|
|
|
Staging drawing approval from Railways |
pending |
1 no yet to be received (RP3-RP4) |
|
Retaining wall (Palakkad side) |
In progress |
100% work done |
|
Kerb Casting (Palakkad side) |
Completed |
|
|
Handrail fixing (Palakkad side) |
Completed |
|
|
Drain work (Moyan school side) |
In progress |
done 40% |
|
Retaining wall,Kerb & Handrail (Moyan school side) |
Completed |
100% completed |
|
Bowstring girder (RP4-RP5) |
Completed |
Done upto bow arch bracing |
|
Handrail fixing & kerb casting |
Completed |
4 slabs of Moyen's side and 2 slabs of Pkd side completed. |
|
Bowstring girder Stressing and grouting |
Completed |
|
|
RP6-RP7-RP8 railway slab |
Completed |
|
|
RP6-RP7-RP8 Kerb & paparapet wall |
Completed |
|
|
RP7-P5, P5-P6, P6-P7, P7-P8 Deck slab and girder |
completed |
Moyen's school side deck slabs |
|
Crash barier for RP6-RP7-RP8 |
Completed |
|
|
P1-P2, P4-RP1 Deck slabs and girder |
Completed |
Pkd side deck slabs |
|
RP5-RP6 girder & deck slab work |
Completed |
|
|
RP5-RP6 Crash barrier |
Completed |
|
|
RP5-RP6 Kerb & paparpet wall |
Completed |
|
|
RP4-RP5 Deck slab casting |
Completed |
Bowstring girder |
|
RP4-RP5 slab lowering |
Completed |
|
|
RP4-RP5 crash barrier/kerb casting |
In progress |
|
|
Approach filling |
Completed |
Moyen's school side & Pkd side |
|
WBM for approach |
Completed |
Moyen's school side |
|
WBM for approach |
In progress |
Pkd side (90% completed) |
|
Cantilver portion of P7-P8 & P1-P2 |
completed |
|
|
RP1-RP2 Staging footing |
Completed |
5 No.s out of 5 No.s done |
|
RP2-RP3 Staging footing |
In progress |
2 No.s out of 3 No.s done |
|
Expansion joint of railway portion(strip seal) |
In progress |
3 out of 3 No.s completed |
|
Diversion road WBM |
Completed |
Moyens side |
|
Painting works |
Stopped |
Moyens & Palakkad side |
|
Ret wall LHS & RHS side I, II & III port |
In progress |
III arm |
|
Piling works in P10, P11, P12 locations |
Completed |
III arm (12 No.s) |
|
Pile cap works in P10 P11 & P12 location |
Completed |
III arm |
|
Pier P10 P11 & P12 |
Completed |
|
|
RP8-P9 girder and deck slab casting |
Completed |
|
|
RP1-RP2 girder and slab casting |
Completed |
|
|
Pier cap P10, P11 |
Completed |
|
|
P9-P10 girder and slab casting |
Completed |
|