Prevoius Weekly Reports
|
24.05.2010 |
|
ROB at Bakel
Work Planned upto 24/05/2010 |
Completed / Progress |
Span of Kasargod side |
|
Staging work |
Completed |
Bar bending |
In progress |
Concreting beam 3 Nos. |
Completed |
Shuttering for deck slab |
In progress |
|
|
Back |
|