Prevoius Weekly Reports

   Weekly Progress Report as on 28.12.2012
    
Sl.
No
Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 - - - - - -
4 PierCap 21 21 - - - - - -
5 Deck Slab 21 19 2 - - - - -
6 Hand Rails 21 15 6   2 1 1 2
7 Expansion Joint 21 14 7   2 1 1 2
8 RC wall - Kuttipuram side 100% 25% 75% - 0% 0% 0% 0%
9 RC wall - Kanjipura side 100% 34% 66%   10% 8% 2% 10%
                   
Date 22.12.12 24.12.12 25.12.12 26.12.12 27.12.12 28.12.12      
Climate Pleasant Pleasant Pleasant Pleasant Pleasant Pleasant      
No. of labours 30 30 30 30 30 30      
                   
                   
Availability of Materials                
                   
Material Required Available              
Fine aggregate 15 m3 18 m3              
Coarse Aggregate 20 m3  25 m3              
Cement 200 bags 250 bags              
Steel 10 MT 25 MT              
 
Back
 
    
HAND RAIL POST VIEW AT KUTTIPURAM SIDE

    
    
VIEW OF KUTTIPURAM SIDE

    
    
RC WALL RAFT IN KANJIPURA SIDE

      
 

 

 

 

 

 

 

 