Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7887134
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress as on 21-12-12
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaining for completion as per the weekly plan Remarks 
1 PILE Muthambi side 27 27 0 0 0 0 0 0   Completed
2 PILE Thamarassery side 33 33 0 0 0 0 0 0   Completed
3 PILE NH SIDE 33 33 0 0 0 0 0 0   Completed
4 PILE CAP Muthambi SIDE 9 9 0 0 0 0 0 0   Completed
5 PILE CAP Thamarassery SIDE 11 11 0 0 0 0 0 0   Completed
6 PILE CAP NH SIDE 10 10 0 0 0 0 0 0   Completed
7 PIER Muthambi  SIDE 9 9 0 0 0 0 0 0   Completed
8 PIER Thamarassery SIDE 11 11 0 0 0 0 0 0   Completed
9 PIER NH SIDE 10 10 0 0 0 0 0 0   Completed
10 PIER CAP Muthambi  SIDE 9 9 0 0 0 0 0 0   Completed
11 PIER CAP Thamarassery SIDE 11 11 0 0 0 0 0 0   Completed
12 PIER CAP NH SIDE 10 10 0 0 0 0 0 0   Completed
13 RE/R WALL Muthambi side 100% 60% 40% 0 20.00% 5.00% 0.15 20.00%    Side wall final lift work in progress in one half and side wall work is in progress in next half.
14 RE/R WALL Thamarassery side SIDE 100% 70% 30% 0 15.00% 0.00% 0.15 15.00%   Land Issue.Raft & side wall 1st lift  done for 25m second side.
15 RE/R WALL NH SIDE 100% 100% 0% 0 0.00% 0.00% 0 0.00%    completed. 
16 BEAM/SLAB Muthambi SIDE 8 8 0 0 0 0 0 0   Completed
17 BEAM/SLAB Thamarassery SIDE 10 10 0 0 0 0 0 0   Completed
18 BEAM/SLAB NH SIDE 11 9 2 0 1 0.5 0.5 0.5 7 Girder completed. Deck slab work in progress
19 HR/FP/KERB Muthambi SIDE 100% 85% 15% 0 0.00% 0.00% 0 0.00%   Kerb casting&Hand rail fixing in progress
20 HR/FP/KERB thamarassery SIDE 100% 85% 15% 0 0.00% 0.00% 0 0.00%   Kerb casting&Hand rail fixing in progress
21 HR/FP/KERB NH SIDE 100% 75% 25% 0 0.00% 0.00% 0 0.00%   Kerb casting&Hand rail fixing in progress
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0 0.00%    
23 Utility shifting             0     KSEB utility shifting started. Shifted 1 post
                       
                       
                       
  Availbility of Men                     
  Date   15-12-12 16-12-12 17-12-12 18-12-12 19-12-12 20-12-12 21-12-12    
  Nof labours   45 33 50 50 47 47 43    
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) 90 80                
  Fine Aggreagate(m3) 75 80                
  Cement(bag) 1400 600                
  Steel(MT) 25 40                
                       
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL                    
  KSEB                    
  KWA                    
  Others                    
 
Back
 
    
WORK IN PROGRESS P7-RP2 GIRDER

    
    
T JUNCTION

    
    
T JUNCTION- GIRDER CONCRETING

    
    
SLUMP TESTING-GIRDER CONCRETING P8-P9 GIRDER

    
 
    
LONG VIEW OF HAND RAILS IN AP3 SIDE FROM T JUNCTION

    
    
AP2 SIDE RETAINING WALL WORK IN PROGRESS

      
 

 

 

 

 

 

 

 

Untitled Document