Si No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
No of days remaining for completion as per the weekly plan |
Remarks |
1 |
PILE Muthambi side |
27 |
27 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Completed |
2 |
PILE Thamarassery side |
33 |
33 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Completed |
3 |
PILE NH SIDE |
33 |
33 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Completed |
4 |
PILE CAP Muthambi SIDE |
9 |
9 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Completed |
5 |
PILE CAP Thamarassery SIDE |
11 |
11 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Completed |
6 |
PILE CAP NH SIDE |
10 |
10 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Completed |
7 |
PIER Muthambi SIDE |
9 |
9 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Completed |
8 |
PIER Thamarassery SIDE |
11 |
11 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Completed |
9 |
PIER NH SIDE |
10 |
10 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Completed |
10 |
PIER CAP Muthambi SIDE |
9 |
9 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Completed |
11 |
PIER CAP Thamarassery SIDE |
11 |
11 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Completed |
12 |
PIER CAP NH SIDE |
10 |
10 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Completed |
13 |
RE/R WALL Muthambi side |
100% |
60% |
40% |
0 |
20.00% |
5.00% |
0.15 |
20.00% |
|
Side wall final lift work in progress in one half and side wall work is in progress in next half. |
14 |
RE/R WALL Thamarassery side SIDE |
100% |
70% |
30% |
0 |
15.00% |
0.00% |
0.15 |
15.00% |
|
Land Issue.Raft & side wall 1st lift done for 25m second side. |
15 |
RE/R WALL NH SIDE |
100% |
100% |
0% |
0 |
0.00% |
0.00% |
0 |
0.00% |
|
completed. |
16 |
BEAM/SLAB Muthambi SIDE |
8 |
8 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Completed |
17 |
BEAM/SLAB Thamarassery SIDE |
10 |
10 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Completed |
18 |
BEAM/SLAB NH SIDE |
11 |
9 |
2 |
0 |
1 |
0.5 |
0.5 |
0.5 |
7 |
Girder completed. Deck slab work in progress |
19 |
HR/FP/KERB Muthambi SIDE |
100% |
85% |
15% |
0 |
0.00% |
0.00% |
0 |
0.00% |
|
Kerb casting&Hand rail fixing in progress |
20 |
HR/FP/KERB thamarassery SIDE |
100% |
85% |
15% |
0 |
0.00% |
0.00% |
0 |
0.00% |
|
Kerb casting&Hand rail fixing in progress |
21 |
HR/FP/KERB NH SIDE |
100% |
75% |
25% |
0 |
0.00% |
0.00% |
0 |
0.00% |
|
Kerb casting&Hand rail fixing in progress |
22 |
BC/PAINTING |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0 |
0.00% |
|
|
23 |
Utility shifting |
|
|
|
|
|
|
0 |
|
|
KSEB utility shifting started. Shifted 1 post |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Availbility of Men |
|
|
|
|
|
|
|
|
|
|
|
Date |
|
15-12-12 |
16-12-12 |
17-12-12 |
18-12-12 |
19-12-12 |
20-12-12 |
21-12-12 |
|
|
|
Nof labours |
|
45 |
33 |
50 |
50 |
47 |
47 |
43 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Material Stocking Status |
Required |
Available |
Remarks |
|
|
|
|
|
|
|
|
Coarse Aggreagate (m3) |
90 |
80 |
|
|
|
|
|
|
|
|
|
Fine Aggreagate(m3) |
75 |
80 |
|
|
|
|
|
|
|
|
|
Cement(bag) |
1400 |
600 |
|
|
|
|
|
|
|
|
|
Steel(MT) |
25 |
40 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Utility shifting |
|
|
|
|
|
|
|
|
|
|
|
Utilities to be shifted |
Status |
Remarks |
|
|
|
|
|
|
|
|
|
BSNL |
|
|
|
|
|
|
|
|
|
|
|
KSEB |
|
|
|
|
|
|
|
|
|
|
|
KWA |
|
|
|
|
|
|
|
|
|
|
|
Others |
|
|
|
|
|
|
|
|
|
|