Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7888399
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   weekly progress graph as on 21.12.2012
    
Progress Report For Mooledam ROB for the week ending on 22-12-2012
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan
1 PILE 21 20 1 1 0 0 1 0 0
2 PILE CAP 7 5 2 0 0 0 0 0 0
3 PIER 9 4 5 0 1 1 0 0 0
4 PIER CAP 9 1 8 0 2 1 1 2 0
 
Back
 
    
PIER CAP P5 & P6 READY FOR CONCRETING

    
    
LOAD TEST IN PROGRESS

      
 

 

 

 

 

 

 

 

Untitled Document