Prevoius Weekly Reports

   Weekly progress report as on 21.12.2012
    
Sl No   Activity Description   Total Quantity  Cumulative progress upto last week   Balance  work up to last week  Cumulative delay in Qty up to last week  Work  planned  during the week   Actual work done during the week   Cumulative delay in Qty up to this week  Work  Planned for next week   Remarks 
1 Pile towards Kadukutty side 26 19 7 1 2 2 0 2  
2 Pile towards Divine Centre side 18 0 0 0 0 0 0 0  
3 Pile cap at Kadukutty  Side 6 0 0 0 0 0 0 0  
4 Pile Cap at Divine centreside 4 0 0 0 0 0 0 0  
5 RC wall at Kadukutty side 100% 0% 0 0 0 0 0 0  
6 RC wall at Divine centre side 100% 0% 0 0 0 0 0 0  
7 Pier at Kadukutty Side 6 0 6 0 0 0 0 0  
8 Pier at Divine centre Side 4 0 4 0 0 0 0 0  
9 Piercap at Kadukutty Side 6 0 6 0 0 0 0 0  
10 Piercap at Divine centre 4 0 4 0 0 0 0 0  
11 PEDESTAL 54 0 54 0 0 0 0 0  
12 Beam and cross beam at Kadukutty side 6 0 6 0 0 0 0 0  
13 Beam and cross beam at Divine centre side  4 0 4 0 0 0 0 0  
14 Deck slab  at Kadukutty side  6 0 6 0 0 0 0 0  
15 Deck slab  at Divine centre side  4 0 4 0 0 0 0 0  
16 Dirt wall  2 0 2 0 0 0 0 0  
17 Kerb Kadukutty side 100% 0% 100% 0% 0% 0% 0% 0%  
18 Kerb Divine centre side 100% 0% 100% 0% 0% 0% 0% 0%  
19 Earth filling in approach embankment  100% 0% 100% 0% 0% 0% 0% 0%  
20 Hand rail fixing -Divine centre side 100% 0% 100% 0% 0% 0% 0% 0%  
21 Hand rail fixing -Kadukutty side 100% 0% 100% 0% 0% 0% 0% 0%  
22 Expansion Joints 7 0 7 0% 0% 0% 0% 0%  
23 WBM  100% 0% 100% 0 0% 0% 0% 0%  
24 Acrylic Elastomeric Membrane Coating 100% 0% 100% 0 50% 50% 0% 0%  
                     
Date 15/12/2012 17/12/2012 18/12/2012 19/12/2012 20/12/2012 21/12/2012        
Climate dry dry dry dry dry dry        
No.of labours 15 12 14 15 15 15        
 
Back
 
    
PILE CHIPPING OF P6

    
    
EXCAVATION AND LINER CUTTING OF P2

    
    
CONCRETING OF P4A

      
 

 

 

 

 

 

 

 