Prevoius Weekly Reports

   Weekly Progress Report as on 14.12.2012
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 - - - - - -
4 PierCap 21 21 - - - - - -
5 Deck Slab 21 19 2 - - - - -
6 Hand Rails 21 14 7   2 1 1 2
7 Expansion Joint 21 11 10   2 2 0 2
8 RC wall - Kuttipuram side 100% 25% 75% - 0% 0% 0% 0%
9 RC wall - Kanjipura side 100% 20% 80%   10% 8% 2% 10%
                   
Date 08.12.12 10.12.12 11.12.12 12.12.12 13.12.12 14.12.12      
Climate Pleasant Pleasant Pleasant Pleasant Pleasant Pleasant      
No. of labours 25 25 25 28 28 28      
                   
                   
Availability of Materials                
                   
Material Required Available              
Fine aggregate 12 m3 18 m3              
Coarse Aggregate 16 m3  20 m3              
Cement 150 bags 200 bags              
Steel 3 MT 10 MT              
 