   Weekly Progress Report as on 14.12.2012
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed    
2 PILE PADANNA SIDE 24 24 Completed    
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed    
4 PILE CAP  PADANNA SIDE 8 8 Completed    
5 PIER CHERUVATHOOR SIDE 9 9 Completed    
6 PIER PADANNA SIDE 8 8 Completed    
7 PIER CAP CHERUVATHOOR SIDE 9 9 Completed    
8 PIER CAP PADANNA SIDE 8 8 Completed    
9 RE/RC WALL CHERUVATHOOR  SIDE 100% 100% Completed   Friction slab and capping complete at both sides.
10 RE/RC  WALL PADANNA SIDE 100% 80% 20% 10% 5.00% 3.00% 2.00% 5.00%   6th layer in progress
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 8 1 complete except railway adjacent span    
12 BEAM/SLAB PADANNA SIDE 8 7 1 complete except railway adjacent span    
13 EXPANSION JOINT CHERUVATHUR SIDE 9 7 2 0 1 1 0 0   AP2 concreted.
14 EXPANSION JOINT PADANNA SIDE 8 6 2 0 0 0 0 1   AP1 Planned
15 KERB CHERUVATHOOR  SIDE 100% 100.00% Completed   complete for Friction slab also.
16 KERB PADANNA SIDE 100% 80% 20% 0 0.00% 0.00% 0.00% 0.00%   complete for slab and RC Wall portion
17 HANDRAIL CHERUVATHUR SIDE 100% 85% 15% 0.00% 10.00% 10.00% 0.00% 5.00%   handrail complete on RHS
18 HANDRAIL PADANNA SIDE 100% 79% 21% 0% 0.00% 0.00% 0.00% 0.00%   RE Panel portion remaining
17 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%   Grinding and finishing works in progress at both sides.
18 Others/Miscellaneous                   Drainage works complete for 100 m at chr side.Another 43 m planned this week.
                       
                       
                      DR Work complete for 4m service road and 7m road.
                       
19 Deck Slab                    
20 Utility shifting                    
                       
                       
                       
  Availbility of Men                     
  Date 08-12-12 09-12-12 ####### 11-12-12 12-12-12 13-12-12 14-12-12      
  No of labours 28 28 28 28 28 28 28      
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) available                
  Fine Aggreagate(m3) available                
  Cement(bag) 80 350              
  Steel(MT) 2 4              
                       
                       
  Utility shifting              
  Utilities to be shifted Status Remarks                
  BSNL shifting complete at Padanna side RE Panel area.OFC was broken on 16-10-12 and was repaired.            
  KSEB   UG Cables obstructing the drainage works infront of unity hospital were removed on 06-12-12.            
  KWA Repaired the pipelines at Padanna RE Panel area.            
  Others                    
 
Back
 
    
PADANNA RE PANEL AREA

    
    
DRAINAGE INFRONT OF VETERINARY HOSPITAL

    
    
CHR SIDE HANDRAIL GRINDING WORK IP

      
 

 

 

 

 

 

 

 