Sl No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
No of days remaing for completion as per the weekly plan |
Remarks |
1 |
PILE CHERUVATHOOR SIDE |
27 |
27 |
Completed |
|
|
2 |
PILE PADANNA SIDE |
24 |
24 |
Completed |
|
|
3 |
PILE CAP CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
|
4 |
PILE CAP PADANNA SIDE |
8 |
8 |
Completed |
|
|
5 |
PIER CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
|
6 |
PIER PADANNA SIDE |
8 |
8 |
Completed |
|
|
7 |
PIER CAP CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
|
8 |
PIER CAP PADANNA SIDE |
8 |
8 |
Completed |
|
|
9 |
RE/RC WALL CHERUVATHOOR SIDE |
100% |
100% |
Completed |
|
Friction slab and capping complete at both sides. |
10 |
RE/RC WALL PADANNA SIDE |
100% |
80% |
20% |
10% |
5.00% |
3.00% |
2.00% |
5.00% |
|
6th layer in progress |
11 |
BEAM/SLAB CHERUVATHOOR SIDE |
9 |
8 |
1 |
complete except railway adjacent span |
|
|
12 |
BEAM/SLAB PADANNA SIDE |
8 |
7 |
1 |
complete except railway adjacent span |
|
|
13 |
EXPANSION JOINT CHERUVATHUR SIDE |
9 |
7 |
2 |
0 |
1 |
1 |
0 |
0 |
|
AP2 concreted. |
14 |
EXPANSION JOINT PADANNA SIDE |
8 |
6 |
2 |
0 |
0 |
0 |
0 |
1 |
|
AP1 Planned |
15 |
KERB CHERUVATHOOR SIDE |
100% |
100.00% |
Completed |
|
complete for Friction slab also. |
16 |
KERB PADANNA SIDE |
100% |
80% |
20% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
complete for slab and RC Wall portion |
17 |
HANDRAIL CHERUVATHUR SIDE |
100% |
85% |
15% |
0.00% |
10.00% |
10.00% |
0.00% |
5.00% |
|
handrail complete on RHS |
18 |
HANDRAIL PADANNA SIDE |
100% |
79% |
21% |
0% |
0.00% |
0.00% |
0.00% |
0.00% |
|
RE Panel portion remaining |
17 |
BC/PAINTING |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
Grinding and finishing works in progress at both sides. |
18 |
Others/Miscellaneous |
|
|
|
|
|
|
|
|
|
Drainage works complete for 100 m at chr side.Another 43 m planned this week. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
DR Work complete for 4m service road and 7m road. |
|
|
|
|
|
|
|
|
|
|
|
|
19 |
Deck Slab |
|
|
|
|
|
|
|
|
|
|
20 |
Utility shifting |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Availbility of Men |
|
|
|
|
|
|
|
|
|
|
|
Date |
08-12-12 |
09-12-12 |
####### |
11-12-12 |
12-12-12 |
13-12-12 |
14-12-12 |
|
|
|
|
No of labours |
28 |
28 |
28 |
28 |
28 |
28 |
28 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Material Stocking Status |
Required |
Available |
Remarks |
|
|
|
|
|
|
|
|
Coarse Aggreagate (m3) |
available |
|
|
|
|
|
|
|
|
|
Fine Aggreagate(m3) |
available |
|
|
|
|
|
|
|
|
|
Cement(bag) |
80 |
350 |
|
|
|
|
|
|
|
|
Steel(MT) |
2 |
4 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Utility shifting |
|
|
|
|
|
|
|
|
Utilities to be shifted |
Status |
Remarks |
|
|
|
|
|
|
|
|
|
BSNL |
shifting complete at Padanna side RE Panel area.OFC was broken on 16-10-12 and was repaired. |
|
|
|
|
|
|
|
KSEB |
|
UG Cables obstructing the drainage works infront of unity hospital were removed on 06-12-12. |
|
|
|
|
|
|
|
KWA |
Repaired the pipelines at Padanna RE Panel area. |
|
|
|
|
|
|
|
Others |
|
|
|
|
|
|
|
|
|
|