Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7887531
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress report as on 14.12.2012
    
Sl No   Activity Description   Total Quantity  Cumulative progress upto last week   Balance  work up to last week  Cumulative delay in Qty up to last week  Work  planned  during the week   Actual work done during the week   Cumulative delay in Qty up to this week  Work  Planned for next week   Remarks 
1 Pile towards Kadukutty side 26 17 9 1 2 2 0 2  
2 Pile towards Divine Centre side 18 0 0 0 0 0 0 0  
3 Pile cap at Kadukutty  Side 6 0 0 0 0 0 0 0  
4 Pile Cap at Divine centreside 4 0 0 0 0 0 0 0  
5 RC wall at Kadukutty side 100% 0% 0 0 0 0 0 0  
6 RC wall at Divine centre side 100% 0% 0 0 0 0 0 0  
7 Pier at Kadukutty Side 6 0 6 0 0 0 0 0  
8 Pier at Divine centre Side 4 0 4 0 0 0 0 0  
9 Piercap at Kadukutty Side 6 0 6 0 0 0 0 0  
10 Piercap at Divine centre 4 0 4 0 0 0 0 0  
11 PEDESTAL 54 0 54 0 0 0 0 0  
12 Beam and cross beam at Kadukutty side 6 0 6 0 0 0 0 0  
13 Beam and cross beam at Divine centre side  4 0 4 0 0 0 0 0  
14 Deck slab  at Kadukutty side  6 0 6 0 0 0 0 0  
15 Deck slab  at Divine centre side  4 0 4 0 0 0 0 0  
16 Dirt wall  2 0 2 0 0 0 0 0  
17 Kerb Kadukutty side 100% 0% 100% 0% 0% 0% 0% 0%  
18 Kerb Divine centre side 100% 0% 100% 0% 0% 0% 0% 0%  
19 Earth filling in approach embankment  100% 0% 100% 0% 0% 0% 0% 0%  
20 Hand rail fixing -Divine centre side 100% 0% 100% 0% 0% 0% 0% 0%  
21 Hand rail fixing -Kadukutty side 100% 0% 100% 0% 0% 0% 0% 0%  
22 Expansion Joints 7 0 7 0% 0% 0% 0% 0%  
23 WBM  100% 0% 100% 0 0% 0% 0% 0%  
24 Acrylic Elastomeric Membrane Coating 100% 0% 100% 0 50% 50% 0% 0%  
                     
Date 12-08-2012 12-10-2012 12-11-2012 12-12-2012 13/12/2012 14/12/2012        
Climate dry dry dry dry dry dry        
No.of labours 15 12 14 15 15 15        
 
Back
 
    
SHIFTING OF RIG FROM P6 TO P4

    
    
CONCRETING OF P6A-B

    
    
BORING OF P4B.

      
 

 

 

 

 

 

 

 

Untitled Document