Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8053778
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   weekly progress as on 7.12.2012
    
Progress Report For Cheruvathoor  ROB for the week ending on 07-12-2012
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed
2 PILE PADANNA SIDE 24 24 Completed
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed
4 PILE CAP  PADANNA SIDE 8 8 Completed
5 PIER CHERUVATHOOR SIDE 9 9 Completed
6 PIER PADANNA SIDE 8 8 Completed
7 PIER CAP CHERUVATHOOR SIDE 9 9 Completed
8 PIER CAP PADANNA SIDE 8 8 Completed
9 RE/RC WALL CHERUVATHOOR  SIDE 100% 100% Completed
10 RE/RC  WALL PADANNA SIDE 100% 78% 22% 10% 10.00% 5.00% 5.00% 10.00%
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 8 1 complete except railway adjacent span
12 BEAM/SLAB PADANNA SIDE 8 7 1 complete except railway adjacent span
13 EXPANSION JOINT CHERUVATHUR SIDE 9 7 2 0 0 0 0 1
14 EXPANSION JOINT PADANNA SIDE 8 6 2 0 0 0 0 0
15 KERB CHERUVATHOOR  SIDE 100% 100.00% Completed
16 KERB PADANNA SIDE 100% 80% 20% 0 0.00% 0.00% 0.00% 0.00%
17 HANDRAIL CHERUVATHUR SIDE 100% 80% 20% 0.00% 0.00% 5.00% 0.00% 10.00%
18 HANDRAIL PADANNA SIDE 100% 79% 21% 0% 0.00% 0.00% 0.00% 0.00%
17 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00% 
 
Back
 
    
KSEB UG CABLE SHIFTING

    
    
GRINDING WORKS IP AT CHR SIDE

    
    
DRAINAGE CONCRETE CHR SIDE

    
    
CHR SIDE RE PANEL HANDRAIL CONCRETE

    
 
    
CHR SIDE RE PANEL HANDRAIL CONCRETE

    
    
4 LAYERS COMPLETE AT PADANNA RE PANEL AREA

      
 

 

 

 

 

 

 

 

Untitled Document