Progress Report For Cheruvathoor ROB for the week ending on 07-12-2012 |
Sl No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
1 |
PILE CHERUVATHOOR SIDE |
27 |
27 |
Completed |
2 |
PILE PADANNA SIDE |
24 |
24 |
Completed |
3 |
PILE CAP CHERUVATHOOR SIDE |
9 |
9 |
Completed |
4 |
PILE CAP PADANNA SIDE |
8 |
8 |
Completed |
5 |
PIER CHERUVATHOOR SIDE |
9 |
9 |
Completed |
6 |
PIER PADANNA SIDE |
8 |
8 |
Completed |
7 |
PIER CAP CHERUVATHOOR SIDE |
9 |
9 |
Completed |
8 |
PIER CAP PADANNA SIDE |
8 |
8 |
Completed |
9 |
RE/RC WALL CHERUVATHOOR SIDE |
100% |
100% |
Completed |
10 |
RE/RC WALL PADANNA SIDE |
100% |
78% |
22% |
10% |
10.00% |
5.00% |
5.00% |
10.00% |
11 |
BEAM/SLAB CHERUVATHOOR SIDE |
9 |
8 |
1 |
complete except railway adjacent span |
12 |
BEAM/SLAB PADANNA SIDE |
8 |
7 |
1 |
complete except railway adjacent span |
13 |
EXPANSION JOINT CHERUVATHUR SIDE |
9 |
7 |
2 |
0 |
0 |
0 |
0 |
1 |
14 |
EXPANSION JOINT PADANNA SIDE |
8 |
6 |
2 |
0 |
0 |
0 |
0 |
0 |
15 |
KERB CHERUVATHOOR SIDE |
100% |
100.00% |
Completed |
16 |
KERB PADANNA SIDE |
100% |
80% |
20% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
17 |
HANDRAIL CHERUVATHUR SIDE |
100% |
80% |
20% |
0.00% |
0.00% |
5.00% |
0.00% |
10.00% |
18 |
HANDRAIL PADANNA SIDE |
100% |
79% |
21% |
0% |
0.00% |
0.00% |
0.00% |
0.00% |
17 |
BC/PAINTING |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |