Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8053478
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   weekly progress as on 7.12.2012
    
Sl No  Activity Description  Total Quantity Cumulative progress upto06.12.02 Balance  work up to 06.12.12 Cumulative delay in Qty up to 06.12.12 Work  planned  during the week  Actual work done during the week delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan
1 PILE  Palarivattom side(Approach portion) 31 31 0 0 0 0 0 0 completed
2 PILE Palarivattom side(railway portion) 6 6 0 0 0 0 0 0
3 PILE vytilla side(Approach portion) 42 42 0 0 0 0 0 0 completed
4 PILE vytilla side(railway portion) 6 6 0 0 0 0 0 0
5 PILE CAP Palarivattom side(Approach portion) 8 8 0 0 0 0 0 0 completed
6 PILE CAP Palarivattom side(railway portion) 1 1 0 0 0 0 0 0 completed
7 PILE CAP vytilla side(Approach portion) 9 9 0 0 0 0 0 0 completed
8 PILE CAP vytilla side(railway portion) 1 1 0 0 0 0 0 0 completed
9 PIER Palarivattom side(Approach portion) 8 8 0 0 0 0 0 0 completed
10 PIER Palarivattomside(railway portion) 1 1 0 0 0 0 0 0 completed
11 PIER Vytilla side(Approach portion) 9 9 0 0 0 0 0 0 completed
12 PIER vytilla side(railway portion) 1 0 1 0 0 0 0 0 completed
13 PIER  CAP Palarivattom side(Approach portion) 8 8 0 0 0 0 0 0 completed
14 PIER  CAP Vytila side(Approach portion) 9 9 0 0 0 0 0 0 completed
15 GIRDER Palarivattom side(Approach portion) 8 7 1 0 0 0 0 0  
16 GIRDER Vytila side(Approach portion) 9 8 1 0 0 0 0 0  
17 DECK SLAB Palarivattom side(Approach portion) 8 7 1 0 0 0 0 0  
18 DECK SLABVytila side(Approach portion) 9 8 1 0 0 0 0 0  
19 PIER CAP Palarivattomside(railway portion) 1 1 0 0 0 0 0 0 completed
20 PIER CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0  
21 RE WALL PANEL CASTING 351 351 0 0 0 0 0 0 completed
20 RE WALL PCC Palarivattom 95 95 0 0 0 0 0 0 completed
21 RE WALL Panel erection Palarivattom 100% 100% 0 0 100% 10% 0% 100% completed
21 RE WALL Earth filling PALARIVATTOM 100% 85% 0.15 0.15 100% 5% 15% 100%  
22 Rly Pile Load test 1 1 0 0 1 1 0 0  
 
Back
 
    
RP1 PIER CAP RFT

    
    
RE WALL PLRVTM

    
    
PIER CAP RP1

    
    
GIRDER RFT P9RP2

    
 
    
GIRDER P9RP2

      
 

 

 

 

 

 

 

 

Untitled Document