Sl No |
Activity Description |
Total Quantity |
Cumulative progress upto06.12.02 |
Balance work up to 06.12.12 |
Cumulative delay in Qty up to 06.12.12 |
Work planned during the week |
Actual work done during the week |
delay in Qty up to this week |
Work Planned for next week |
No of days remaing for completion as per the weekly plan |
1 |
PILE Palarivattom side(Approach portion) |
31 |
31 |
0 |
0 |
0 |
0 |
0 |
0 |
completed |
2 |
PILE Palarivattom side(railway portion) |
6 |
6 |
0 |
0 |
0 |
0 |
0 |
0 |
3 |
PILE vytilla side(Approach portion) |
42 |
42 |
0 |
0 |
0 |
0 |
0 |
0 |
completed |
4 |
PILE vytilla side(railway portion) |
6 |
6 |
0 |
0 |
0 |
0 |
0 |
0 |
5 |
PILE CAP Palarivattom side(Approach portion) |
8 |
8 |
0 |
0 |
0 |
0 |
0 |
0 |
completed |
6 |
PILE CAP Palarivattom side(railway portion) |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
completed |
7 |
PILE CAP vytilla side(Approach portion) |
9 |
9 |
0 |
0 |
0 |
0 |
0 |
0 |
completed |
8 |
PILE CAP vytilla side(railway portion) |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
completed |
9 |
PIER Palarivattom side(Approach portion) |
8 |
8 |
0 |
0 |
0 |
0 |
0 |
0 |
completed |
10 |
PIER Palarivattomside(railway portion) |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
completed |
11 |
PIER Vytilla side(Approach portion) |
9 |
9 |
0 |
0 |
0 |
0 |
0 |
0 |
completed |
12 |
PIER vytilla side(railway portion) |
1 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
completed |
13 |
PIER CAP Palarivattom side(Approach portion) |
8 |
8 |
0 |
0 |
0 |
0 |
0 |
0 |
completed |
14 |
PIER CAP Vytila side(Approach portion) |
9 |
9 |
0 |
0 |
0 |
0 |
0 |
0 |
completed |
15 |
GIRDER Palarivattom side(Approach portion) |
8 |
7 |
1 |
0 |
0 |
0 |
0 |
0 |
|
16 |
GIRDER Vytila side(Approach portion) |
9 |
8 |
1 |
0 |
0 |
0 |
0 |
0 |
|
17 |
DECK SLAB Palarivattom side(Approach portion) |
8 |
7 |
1 |
0 |
0 |
0 |
0 |
0 |
|
18 |
DECK SLABVytila side(Approach portion) |
9 |
8 |
1 |
0 |
0 |
0 |
0 |
0 |
|
19 |
PIER CAP Palarivattomside(railway portion) |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
completed |
20 |
PIER CAP vytilla side(railway portion) |
1 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
|
21 |
RE WALL PANEL CASTING |
351 |
351 |
0 |
0 |
0 |
0 |
0 |
0 |
completed |
20 |
RE WALL PCC Palarivattom |
95 |
95 |
0 |
0 |
0 |
0 |
0 |
0 |
completed |
21 |
RE WALL Panel erection Palarivattom |
100% |
100% |
0 |
0 |
100% |
10% |
0% |
100% |
completed |
21 |
RE WALL Earth filling PALARIVATTOM |
100% |
85% |
0.15 |
0.15 |
100% |
5% |
15% |
100% |
|
22 |
Rly Pile Load test |
1 |
1 |
0 |
0 |
1 |
1 |
0 |
0 |
|