   weekly progress as on 7.12.2012
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 - - - - - -
4 PierCap 21 21 - - - - - -
5 Deck Slab 21 19 2 - - - - -
6 Hand Rails 21 13 8   2 1 1 2
7 Expansion Joint 21 10 11   2 1 1 2
8 RC wall - Kuttipuram side 100% 25% 75% - 0% 0% 0% 0%
9 RC wall - Kanjipura side 100% 16% 84%   10% 5% 5% 10%
 
Back
 
    
RC WALL SHUTTERING IN KANJIPURA SIDE

    
    
SLAB AND HAND RAILPOST AT KUTTIPURAM SIDE

    
    
RC WALL AND HAND RAIL POST AT KUTTIPURAM SIDE

    
    
HANDRAIL POST AT KUTTIPURAM SIDE

    
 
 
 

 

 

 

 

 

 

 