   30.07.2010
    

ROB at Mulamkunnathukavu

Description Remarks
GAD submitted Revised GAD received on 27.07.10. Comments are forwarded to GPT.  The levels shall be verified at site. 
Sub structure & Foundation Foundation & sub structure details are submitted on 16.07.10.  However, the pile capacity calculation as per soil status is not yet received.
Superstructure
Not yet received
 
Proof checking is pending due to supporting calculations of  super structure.
 
 