Details are of the work done between 2nd and 7th of November
Work Planned |
Completed/Progress |
Delay |
Staging work EKM side |
completed |
|
Staging work beam bottom |
In Progress |
|
Barbending for Girders |
Both span in Progress |
|
Staging work on Thammanam side not started |
|
Due to the leakage of water line |
|