   Weekly progress report as on 30.11.2012
    
Sl No   Activity Description   Total Quantity  Cumulative progress upto last week   Balance  work up to last week  Cumulative delay in Qty up to last week  Work  planned  during the week   Actual work done during the week   Cumulative delay in Qty up to this week  Work  Planned for next week   Remarks 
1 Pile towards Kadukutty side 25 14 11 0 3 2 1 3  
2 Pile towards Divine Centre side 16 0 0 0 0 0 0 0  
3 Pile cap at Kadukutty  Side 6 0 0 0 0 0 0 0  
4 Pile Cap at Divine centreside 4 0 0 0 0 0 0 0  
5 RC wall at Kadukutty side 100% 0% 0 0 0 0 0 0  
6 RC wall at Divine centre side 100% 0% 0 0 0 0 0 0  
7 Pier at Kadukutty Side 6 0 6 0 0 0 0 0  
8 Pier at Divine centre Side 4 0 4 0 0 0 0 0  
9 Piercap at Kadukutty Side 6 0 6 0 0 0 0 0  
10 Piercap at Divine centre 4 0 4 0 0 0 0 0  
11 PEDESTAL 54 0 54 0 0 0 0 0  
12 Beam and cross beam at Kadukutty side 6 0 6 0 0 0 0 0  
13 Beam and cross beam at Divine centre side  4 0 4 0 0 0 0 0  
14 Deck slab  at Kadukutty side  6 0 6 0 0 0 0 0  
15 Deck slab  at Divine centre side  4 0 4 0 0 0 0 0  
16 Dirt wall  2 0 2 0 0 0 0 0  
17 Kerb Kadukutty side 100% 0% 100% 0% 0% 0% 0% 0%  
18 Kerb Divine centre side 100% 0% 100% 0% 0% 0% 0% 0%  
19 Earth filling in approach embankment  100% 0% 100% 0% 0% 0% 0% 0%  
20 Hand rail fixing -Divine centre side 100% 0% 100% 0% 0% 0% 0% 0%  
21 Hand rail fixing -Kadukutty side 100% 0% 100% 0% 0% 0% 0% 0%  
22 Expansion Joints 7 0 7 0% 0% 0% 0% 0%  
23 WBM  100% 0% 100% 0 0% 0% 0% 0%  
24 Acrylic Elastomeric Membrane Coating 100% 0% 100% 0 50% 50% 0% 0%  
                     
Date 24/11/12 26/11/12 27/11/12 28/11/12 29/11/12 30/11/2012        
Climate dry dry dry dry dry dry        
No.of labours 13 13 14 13 13 13        
 
Back
 
    
CONCRETING OF P6C

    
    
CONCRETING OF P6B

    
    
BORING OF P6B

    
    
BORING OF P6A

    
 
 
 

 

 

 

 

 

 

 