   Weekly Progress Report as on 30.11.2012
    
Progress Report - ROB-Thirunavaya   -30.11.2012
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 - - - - - -
4 PierCap 21 21 0 - - - - -
5 Deck Slab 21 18 3 - 0 1 0 -
6 Hand Rails 21 11 10   2 2 0 2
7 Expansion Joint 21 9 12   2 1 1 2
8 RC wall - Kuttipuram side 100% 25% 75% - 0% 0% 0% 0%
9 RC wall - Kanjipura side 100% 16% 84%   10% 0% 10% 10%
                   
Date 24.11.12 26.11.12 27.11.12 28.11.12 29.11.12 30.11.12      
Climate Pleasant Pleasant Pleasant Pleasant Pleasant Pleasant      
No. of labours 47 47 30 30 30 30      
                   
                   
Availability of Materials                
                   
Material Required Available              
Fine aggregate 15 m3 15 m3              
Coarse Aggregate 20 m3 5 m3              
Cement 200 bags 300 bags              
Steel 6 MT 15 MT              
 