   Weekly Progress Report as on 23.11.2012
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed    
2 PILE PADANNA SIDE 24 24 Completed    
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed    
4 PILE CAP  PADANNA SIDE 8 8 Completed    
5 PIER CHERUVATHOOR SIDE 9 9 Completed    
6 PIER PADANNA SIDE 8 8 Completed    
7 PIER CAP CHERUVATHOOR SIDE 9 9 Completed    
8 PIER CAP PADANNA SIDE 8 8 Completed    
9 RE/RC WALL CHERUVATHOOR  SIDE 100% 96% 4% 4% 2.00% 2.00% 2.00% 2.00%   Friction slab and capping complete at both sides.
10 RE/RC  WALL PADANNA SIDE 100% 68% 32% 5% 10.00% 5.00% 5.00% 10.00%   Third layer erection complete,alignment works in progress.
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 8 1 complete except railway adjacent span    
12 BEAM/SLAB PADANNA SIDE 8 7 1 complete except railway adjacent span    
13 EXPANSION JOINT CHERUVATHUR SIDE 9 7 2 0 0 0 0 0   complete except AP2 and P8
14 EXPANSION JOINT PADANNA SIDE 8 6 2 0 0 0 0 0   complete except AP1 and P7
15 KERB CHERUVATHOOR  SIDE 100% 87.00% 13% 0 13.00% 13.00% 0.00% 0.00%   complete for Friction slab also.
16 KERB PADANNA SIDE 100% 80% 20% 0 0.00% 0.00% 0.00% 0.00%   complete for slab and RC Wall portion
17 HANDRAIL CHERUVATHUR SIDE 100% 80% 20% 0.00% 0.00% 0.00% 0.00% 0.00%   RE Panel portion remaining
18 HANDRAIL PADANNA SIDE 100% 79% 21% 0% 0.00% 0.00% 0.00% 0.00%   RE Panel portion remaining
17 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%   Grinding and finishing works restarted on 21-11-12
18 Others/Miscellaneous                   Drainage works complete for 56 m at chr side.First lift complete for 21m drainage.REMAINING WORKS IN PROGRESS.
                       
                       
                      DR Work complete for 4m service road and 7m road.
                       
19 Deck Slab                    
20 Utility shifting                    
                       
                       
                       
  Availbility of Men                     
  Date 17-11-12 18-11-12 19-11-12 20-11-12 21-11-12 22-11-12 23-11-12      
  No of labours 16 16 19 30 30 30 30      
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) available                
  Fine Aggreagate(m3) available                
  Cement(bag) 100 501              
  Steel(MT) 1 5              
                       
                       
  Utility shifting              
  Utilities to be shifted Status Remarks                
  BSNL shifting complete at Padanna side RE Panel area.OFC was broken on 16-10-12 and repaired.            
  KSEB   electric post infront of unity hospital  need to be shifted urgently,currently not affecting the works.AXE and AE visited the site on 27-09-12.Lines over RC Wall Padanna side shifted.            
  KWA Repaired the pipelines at Padanna RE Panel area.            
  Others                    
                       
                       
                       
 
Back
 
    
RE PANEL 3RD ERECTION IP

    
    
GUARD STONE FIXING IP AT CHR SIDE

    
    
FRICTION SLAB CAPPING CONCRETE IP

      
 

 

 

 

 

 

 

 