   Weekly Progress Report as on 23.11.2012
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 - - - - - -
4 PierCap 21 21 0 - - - - -
5 Deck Slab 21 18 3 - 0 0 0 Re inforcement Work
6 Hand Rails 21 11 10   2 1 1 2
7 Expansion Joint 21 9 12   2 1 1 2
8 RC wall - Kuttipuram side 100% 25% 75% - 0% 0% 0% 0%
9 RC wall - Kanjipura side 100% 8% 92%   10% 8% 2% 10%
                   
Date 17.11.12 19.11.12 20.11.12 21.11.12 22.11.12 23.11.12      
Climate Pleasant Pleasant Pleasant Pleasant Pleasant Rain      
No. of labours 47 47 47 45 45 43      
                   
                   
Availability of Materials                
                   
Material Required Available              
Fine aggregate 20 m3 24 m3              
Coarse Aggregate 21 m3 25 m3              
Cement 200 bags 300 bags              
Steel 15 MT 18 MT              
                   
 
Back
 
    
CROSS BEAM REINFORCEMENT IN P9-P10

    
    
RC WALL WORK AT KANJIPURA SIDE

    
    
DECK SLAB IN P9-P10

      
 

 

 

 

 

 

 

 