Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8053367
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly Progress Report as on 23.11.2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto 22.11.12 Balance  work up to 22.11.12 Cumulative delay in Qty up to 22.11.12 Work  planned  during the week  Actual work done during the week delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE  Palarivattom side(Approach portion) 31 31 0 0 0 0 0 0 completed KWA line to be shifted. Will be over by 18.01.12. work completed on 23.01.12.Rig erected at P9
2 PILE Palarivattom side(railway portion) 6 6 0 0 0 0 0 0
3 PILE vytilla side(Approach portion) 42 42 0 0 0 0 0 0 completed Pipe line broken on 26.01.12 at 2.20 am while boring.Repaired on 26.01.12
4 PILE vytilla side(railway portion) 6 6 0 0 0 0 0 0 RP1 P4 done . RP1 P5 was abandoned due to pile choking. Pile layout to be redesigned.Piling resumed on 29.02.12. Piling held up pending approval  fron RLY. Piling commenced on 06.06.12.
5 PILE CAP Palarivattom side(Approach portion) 8 8 0 0 0 0 0 0 completed P15, P14, A2, P13, P12, P11, P10, P9
6 PILE CAP Palarivattom side(railway portion) 1 1 0 0 0 0 0 0 completed RP2
7 PILE CAP vytilla side(Approach portion) 9 9 0 0 0 0 0 0 completed P1,  P2, P4, P3, A1, P5,P6, P7,P8
8 PILE CAP vytilla side(railway portion) 1 1 0 0 0 0 0 0 completed RP1
9 PIER Palarivattom side(Approach portion) 8 8 0 0 0 0 0 0 completed A2, P15, P14, P13,  P12,  P11, P10, P9 
10 PIER Palarivattomside(railway portion) 1 1 0 0 0 0 0 0 completed RP2
11 PIER Vytilla side(Approach portion) 9 9 0 0 0 0 0 0 completed P1, P2, P3, P4, A1,P5,P6,P7, P8
12 PIER vytilla side(railway portion) 1 0 1 0 0 0 0 0 completed RP1
13 PIER  CAP Palarivattom side(Approach portion) 8 8 0 0 0 0 0 0 completed P15, P14, A2, P13, P12, P11, P10, P9
14 PIER  CAP Vytila side(Approach portion) 9 9 0 0 0 0 0 0 completed P1, P2, P3, A1,P4,P5,P6,P7, P8
15 GIRDER Palarivattom side(Approach portion) 8 7 1 0 0 0 0 0   A2 P15,P15 P14,P14 P13, P13 P12, P11 P10, P12 P11, P10P9
16 GIRDER Vytila side(Approach portion) 9 8 1 0 0 0 0 0   P1P2,  A1P1, P2P3, P3P4, P5P6, P6P7, P4P5, P7P8
17 DECK SLAB Palarivattom side(Approach portion) 8 7 1 0 0 0 0 0   A2 P15, P15 P14, P14 P13,  P13 P12, P11P10, P12 P11, P10P9
18 DECK SLABVytila side(Approach portion) 9 7 2 0 0 0 0 0   P1P2,A1P1, P2P3, P3P4, P4P5, P5P6, P6P7
19 PIER CAP Palarivattomside(railway portion) 1 0 1 0 0 0 0 0 completed RP2
20 PIER CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0    
21 RE WALL PANEL CASTING 351 351 0 0 0 0 0 0 completed  
20 RE WALL PCC Palarivattom 95 95 0 0 0 0 0 0   Rerouting of water connection to photostat shop  by KWA to the completed on 24.03.12. on 24.04.12 the entire RE Wall area was cleared for excavation.
21 RE WALL Panel erection Palarivattom 100% 75% 0.25 0.3 100% 0% 25% 100%   Rerouting of water connection to photostat shop  by KWA to the completed on 24.03.12. on 24.04.12 the entire RE Wall area was cleared for excavation.Panel erection commenced on 15.05.12. No work due to rain. Work resumed on 30.07.12. work held up again.
21 RE WALL Earth filling PALARIVATTOM 100% 35% 0.65 73 100% 8% 65% 50%   Earth filling not done due to rain.Work resumed on 30.07.12. work restarted on 09.10.12.work held up due to rain at night. The area is drenched and could not be rolled due to the high water content.
22 Rly Pile Load test 1 1 0 0 1 1 0 0   completed
 
Back
 
    
RE WALL ROLLING

    
    
RE WALL DENSITY CHECK

    
    
RP2 PEDESTAL

      
 

 

 

 

 

 

 

 

Untitled Document