   Weekly progress report as on 23.11.2012
    
Progress Report For Mooledam ROB for the week ending on 23-11-2012  
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE 21 14 7 2 6 6 0 0 0 Shifting of overhead lines necessary for the remaining pile
2 PILE CAP 7 0 7 1 2 1 2 2 0  
                       
 
Back
 
    
CONCRETING OF PILE CAP AT P2

      
 

 

 

 

 

 

 

 