Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7888005
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress report as on 23.11.2012
    
PROGRESS OF ROB and ROAD  WORK AS ON 23-11-2012.
  Description Completed/ Progress Remarks
IV ROB at Parappanangady    
  Pier cap (Total no of pier Cap- 21) Completed 21 NOS COMPLETED
  RE Wall panel casting ( total600 nos) Completed Errection completed.
  Slab calicut side  (total 10 nos ) Completed  10 nos, adjacent span completed.
  slab NH side ( 11 nos) Completed  11 nos,adjacent span completed.
  Retaining wall NH side completed completed
  Retaining wall calicut side completed  completed
  Dirt wall AP2 concreting  completed Done 100%
  Dirt wall AP1 concreting  completed Done 100%
  Handrail casting completed 1400 nos completed.
  Adjacent span RP1-P9 completed completed.
  Adjacent span RP4-P10 completed completed.
  Handrail fixing completed  completed.
  NH side RE panel errection completed 100% completed.
  RE wall work calicut side. completed 100% completed.
  expansion joint  completed completed.
  painting-slab completed Existing structures completed (adjacent span balance ).
  RAILWAY PORTION    
  Pilling work  Completed piling completed.
   RP1 In progress pier ,piercap completed.
   RP2 In progress pier & piercap completed.
   RP3 In progress pier & piercap completed.
   RP3 In progress pier &piercap completed.
  TEMPERORY STAGING-CENTER SPAN In progress foundations work completed.
 
Back
 
    
ROAD WORK COMPLETED IN NH SIDE.

    
    
STANCHIONS ARE READY TO ERRECT.

    
    
RAILWAY PORTION WORKS IN PROGRESS.

      
 

 

 

 

 

 

 

 

Untitled Document