Prevoius Weekly Reports

   Weekly progress report as on 23.11.2012
    

WORK COMPLETED IN EACH LOCATION OF RAILWAY PORTION

P1 location: Piling completed (4 piles), pile cap, trestle column, trestle beam.

P7 location: 5 pile concreting completed, pile cap, trestle column, trestle beam

 

P8 location: Piling completed (5 piles), pile cap, Trestle column, trestle beam

P2 location: Piling completed (4 piles), pile cap, trestle column, trestle beam.

 

Approach portion at N.H side completed 90%

 

WORK COMPLETED AT PULIKKAKADAVU SIDE

All deck slab concreting completed at pulikkakadavu side.

Works completed upto the road works, miscellaneous works, in the approach portion at pulikkakadavu side.

WORKS BALANCE

P1-P7 superstructure (RCC structure)

P7-P8 superstructure (CENTRAL SPAN)

P8-P2 superstructure (RCC structure

 
Back
 
    
REINFORCEMENT WORK FOR ADJACENT SPAN IN PULIKKAKADAVU SIDE

    
    
REINFORCEMENT TYING WORK FOR THE ADJACENT SPAN IN KORATTY

    
    
CRASH BARRIER REINFORCEMENT IN THE ADJACENT SPAN

      
 

 

 

 

 

 

 

 