Weekly progress report as on 23.11.2012 | |
WORK COMPLETED IN EACH LOCATION OF RAILWAY PORTION P1 location: Piling completed (4 piles), pile cap, trestle column, trestle beam. P7 location: 5 pile concreting completed, pile cap, trestle column, trestle beam
P8 location: Piling completed (5 piles), pile cap, Trestle column, trestle beam P2 location: Piling completed (4 piles), pile cap, trestle column, trestle beam.
Approach portion at N.H side completed 90%
WORK COMPLETED AT PULIKKAKADAVU SIDE All deck slab concreting completed at pulikkakadavu side. Works completed upto the road works, miscellaneous works, in the approach portion at pulikkakadavu side. WORKS BALANCE P1-P7 superstructure (RCC structure) P7-P8 superstructure (CENTRAL SPAN) P8-P2 superstructure (RCC structure | |