   Weekly progress as on 16.11.2012
    
Progress Report For Devdhar ROB for the week ending on 16-11-2012
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week 
1 PILE  CALICUT  SIDE 48 48 0 1 0 0 1 0
2 PILE THIRUR SIDE 24 24 0 11 0 0 11 0
3 PILE CAP CALICUT  SIDE 12 12 0 1 0 0 1 0
4 PILE CAP  THIRURSIDE 6 6 0 5 0 0 5 0
5 PIER CALICUT SIDE 12 12 0 1 0 0 1 0
6 PIER THIRUR SIDE 6 6 0 1 0 0 1 0
7 PIER CAPCALICUT   SIDE 12 12 0 2 0 0 2 0
8 PIER CAP THIRUR SIDE 6 6 0 3 0 0 3 0
9 RETAINING WALL WALL CALICUT   SIDE 100% 65.00% 35% 0 0.00% 0.00% 30.00% 0.00%
10 RETAINING WALL THIRUR SIDE 100% 85% 15% 0 5.00% 5.00% 70.00% 0.00%
11 BEAM CALICUT   SIDE 12 11 1 0 0 0 7 0
12 SLAB CALICUT SIDE 12 10 2   1 1 9 0
13 BEAM THIRUR SIDE 6 1 5 0 1 0 9 1
14 SLAB TIRUR SIDE 6 4 2 0 1 1 1 0
15 HR/FP/KERB CALICUT   SIDE 100% 65% 35% 0 5.00% 5.00% 5.00% 5.00%
16 HR/FP/KERBTHIRUR SIDE 100% 25% 75% 0 5.00% 5.00% 0.00% 15.00%
17 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%
18 Culvert calicut side 100% 15% 85% 0 10.00% 0.00% 20.00% 10.00%
                   
                   
                   
  Availbility of Men               
  Date 10-11-2012 11-11-2012 12-11-2012 13-11-2012 14-11-2012 15-11-2012 16-11-2012  
  Nof labours 23 23 32 32 32 32 32  
                   
                   
  Utility shifting                
  Utilities to be shifted Status Remarks            
  BSNL shifting completed              
  KSEB shifting in progress              
  KWA shifting completed              
  Others                
 
Back
 
    
RETAINING WALL WORKS IN PROGRESS

    
    
TIRUR SIDE APPROACH.

    
    
HANDRAIL CASTING AT P1-P2.

    
    
RETAINING WALL AT CALICUT SIDE

    
 
    
CALICUT SIDE RETAINING WALL WORKS

      
 

 

 

 

 

 

 

 