02.06.2010 |
|
ROB at Bakel
PROGRESS OF ROB WORK AS ON 29.05.2010 |
Work Planned upto 29/05/2010 |
Completed / Progress |
Span of Kasargod side |
|
Concreting beam 3 Nos. |
Completed |
Bar bending for slab |
Completed |
Shuttering work for Slab |
In progress |
|
|