Prevoius Weekly Reports
|
02.06.2010 |
| |
ROB at Bakel
|
PROGRESS OF ROB WORK AS ON 29.05.2010 |
|
Work Planned upto 29/05/2010 |
Completed / Progress |
|
Span of Kasargod side |
|
|
Concreting beam 3 Nos. |
Completed |
|
Bar bending for slab |
Completed |
|
Shuttering work for Slab |
In progress |
|
| |