   Weekly progress as on 16.11.2012
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 - - - - - -
4 PierCap 21 21 0 - - - - -
5 Deck Slab 21 18 3 - 0 0 0 Re inforcement Work
6 Hand Rails 21 10 11   2 1 1 2
7 Expansion Joint 21 7 14   2 0 1 2
8 RC wall - Kuttipuram side 100% 25% 75% - 0% 0% 0% 0%
9 RC wall - Kanjipura side 100% 8% 92%   10% 0% 10% 10%
                   
Date 10.11.12 12.11.12 13.11.12 14.11.12 15.11.12 16.11.12      
Climate Pleasant Pleasant Pleasant Pleasant Pleasant Pleasant      
No. of labours 47 47 37 47 47 47      
                   
                   
Availability of Materials                
                   
Material Required Available              
Fine aggregate 22 m3 28 m3              
Coarse Aggregate 25 m3 30 m3              
Cement 150 bags 100 bags              
Steel 18 MT 25 MT              
 
Back
 
    
RCC WALL AT KANCHIPURA SIDE

    
    
STAGING IN BETWEEN P09 - P10

    
    
REINFORCEMENT FOR BEEMP09 - P10

    
    
REINFORCEMENT FOR BEEM P9 - P10

    
 
    
RCC WALL AT KANCHIPURA SIDE

      
 

 

 

 

 

 

 

 