   5.12.2009
    

Details of work done between 30th Nov to 5th Dec 2009

Work Planned upto 05.12.2009 Completed/Progress Delay
Concreting beams on Ernakulam side Completed  
Shuttering for slab Ernakulam side Completed  
Bar fixing for slab Ernakulam side in progress  
Barbending for Girders PSC span in Progress  
Staging work on Thammanam side In progress  
 